Natural gas power plant · Butler, KS

Augusta Electric Plant No 2

Augusta Electric Plant No 2 is a 21 MW natural gas power plant in Butler County, Kansas, operated by City of Augusta - (KS). Its oldest generator still running came online in 1968. In 2025 it generated 0.8 GWh, about what 76 average Kansas homes use in a year.

Capacity21 MWNameplate, September 2026
Generated0.8 GWhIn 2025
Capacity factor0%Share of the most it could make, 2025
Generators4Oldest from 1968

Augusta Electric Plant No 2 in context

Among the 54 natural gas plants in Kansas in the EIA's inventory, it is the 26th largest, about 0.5% of the state's 4.2 GW of natural gas capacity.

Butler County has 6 power plants of 1 MW or more with 223 MW in all; Augusta Electric Plant No 2 is 9% of that and the 2nd largest of 3 natural gas plants there.

Its capacity factor of 0% in 2025 is lower than the 23% typical for natural gas plants across the US.

The average electricity customer in Butler County goes 2.2 hours a year without power, the 62nd most of 81 counties in Kansas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0123420182019202020212022202320242025GWh 1
0123420192021202320251

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Augusta Electric Plant No 2 (outlined) and other plants in Butler County, shaded. 37.686, -96.965.

Plant facts

Operator
City of Augusta - (KS)
Sector
Electric Utility
Grid operator
SWPP
County
Butler County, KS
EIA plant ID
6791
Where Kansas's power comes from → Kansas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
4 Natural Gas Internal Combustion Engine 6.7 MW 2005 –
3 Natural Gas Internal Combustion Engine 6.0 MW 1981 –
1 Natural Gas Internal Combustion Engine 4.0 MW 1968 –
2 Natural Gas Internal Combustion Engine 4.0 MW 1968 –

Nearby

Other plants in Butler County

Elk River Wind · 150 MWEl Dorado Refinery · 39 MWAugusta Electric Plant No 1 · 12 MWPrairie Sky Solar Farm · 1.0 MWDeGraff Butler Electric · 1.0 MW

Questions

Augusta Electric Plant No 2, answered

How much power does Augusta Electric Plant No 2 produce?

Augusta Electric Plant No 2 has 21 MW of capacity from 4 generators. In 2025 it generated 0.8 GWh, 0% of the most it could have made running flat out all year (its capacity factor).

How many homes does Augusta Electric Plant No 2 power?

Its 2025 output of 0.8 GWh equals the yearly electricity use of about 76 average Kansas homes (876 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Augusta Electric Plant No 2?

Augusta Electric Plant No 2 is in Butler County, Kansas, at about 37.686°, -96.965°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Butler County goes 2.2 hours a year without power, the 62nd most of 81 counties in Kansas. The county's page has the full outage record.

Who operates Augusta Electric Plant No 2?

It is operated by City of Augusta - (KS) (EIA sector: Electric Utility), and it feeds the Southwest Power Pool.

When did Augusta Electric Plant No 2 open?

Its oldest generator still running came online in 1968.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Kansas home's 876 kWh a month in 2025. Methodology.