Solar power plant · Citrus, FL
Bay Trail Solar Power Plant
Bay Trail Solar Power Plant is a 75 MW solar power plant in Citrus County, Florida, operated by Duke Energy Florida, LLC. Its oldest generator still running came online in 2022. In 2025 it generated 164 GWh, about what 12,000 average Florida homes use in a year.
Bay Trail Solar Power Plant in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 21st largest, about 0.5% of the state's 14 GW of solar capacity.
Citrus County has 2 power plants of 1 MW or more with 3.5 GW in all; Bay Trail Solar Power Plant is 2% of that.
Its capacity factor of 25% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Citrus County goes 7.3 hours a year without power, the 39th most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Bay Trail Solar Power Plant (outlined) and other plants in Citrus County, shaded. 29.000, -82.672.
Plant facts
- Operator
- Duke Energy Florida, LLC
- Sector
- Electric Utility
- Grid operator
- FPC
- County
- Citrus County, FL
- EIA plant ID
- 64145
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 75 MW | 2022 | – |
Nearby
Other plants in Citrus County
Questions
Bay Trail Solar Power Plant, answered
How much power does Bay Trail Solar Power Plant produce?
Bay Trail Solar Power Plant has 75 MW of capacity from one generator. In 2025 it generated 164 GWh, 25% of the most it could have made running flat out all year (its capacity factor).
How many homes does Bay Trail Solar Power Plant power?
Its 2025 output of 164 GWh equals the yearly electricity use of about 12,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Bay Trail Solar Power Plant?
Bay Trail Solar Power Plant is in Citrus County, Florida, at about 29.000°, -82.672°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Citrus County goes 7.3 hours a year without power, the 39th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Bay Trail Solar Power Plant?
It is operated by Duke Energy Florida, LLC (EIA sector: Electric Utility), and it feeds balancing authority FPC.
When did Bay Trail Solar Power Plant open?
Its oldest generator still running came online in 2022.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.