Where the power comes from · 2025

Florida

Natural gas made 73% of the electricity generated in Florida in 2025, the 5th highest natural gas share of any state. In 2005, coal made 28% of it; in 2025, 4%.

Generated268 TWh2025 · 2nd of 51
Capacity81 GWNameplate, September 2026
Power plants348With a generator of 1 MW or more
Renewable11%Of generation · US 24%

The mix

Florida's electricity by source

Share of utility-scale generation each year, 1990–2025. Hover a year for every source.

CoalOtherNuclearSolarNatural gasHydro
0%25%50%75%100%19901995200020052010201520202025Natural gas73%Solar9.3%Nuclear11%
CoalOtherNuclearSolarNatural gasHydro
0%25%50%75%100%1990200020102020

Every plant

Florida's power plants

348 plants with a generator of 1 MW or more, sized by capacity and colored by main source, as of September 2026. Click one to open it.

Capacity by source

  • Natural gas55 GW68%
  • Solar13 GW17%
  • Nuclear3.9 GW4.8%
  • Coal3.7 GW4.6%
  • Other3.5 GW4.3%
  • Storage1.2 GW1.5%
  • Hydro44 MW<0.1%

Built and retired

What came online, what shut down

Nameplate capacity that entered service (above the line) and retired (below) in Florida, by year. 2026 runs through September 2026.

HydroNatural gasSolarNuclearStorageOtherCoal
-6 GW-4 GW-2 GW02 GW4 GW6 GW20052010201520202025Built ↑Retired ↓
HydroNatural gasSolarNuclearStorageOtherCoal
-6 GW-4 GW-2 GW02 GW4 GW6 GW20052010201520202025Built ↑Retired ↓

Carbon

CO₂ for every megawatt-hour

Florida's power plants emitted 348 kg of CO₂ for each MWh they generated in 2024, against 597 kg in 2005: the 26th lowest of 51. 93 million metric tons in all.

020040060080019901991199219931994199519961997199819992000200120022003200420052006200720082009201020112012201320142015201620172018201920202021202220232024Florida 348US 356
FloridaUS
0200400600800199420002006201220182024348356

Florida among the states

  1. Generation268 TWh2nd
  2. Renewable share11%39th
  3. Carbon-free share22%41st
  4. Cleanest electricity (kg CO₂/MWh, 2024)34826th
  5. Natural gas share73%5th
  6. Nuclear share11%24th
  7. Solar share9.3%12th
  8. Coal share3.8%36th
All state rankings →

Plants

The largest plants in Florida

By nameplate capacity, with 2025 generation and capacity factor: generation over the most the plant could make running flat out all year.

PlantSourceCountyCapacityGeneratedCapacity factorSince
West County Energy Center Natural gas Palm Beach 4.3 GW 19 TWh 50% 2009
Crystal River Natural gas Citrus 3.4 GW 15 TWh 51% 1982
Turkey Point Nuclear Miami-Dade 3.0 GW 21 TWh 79% 1972
Manatee Natural gas Manatee 3.0 GW 7.1 TWh 28% 1976
Fort Myers Natural gas Lee 2.7 GW 9.0 TWh 38% 1958
Martin Natural gas Martin 2.4 GW 8.0 TWh 37% 1994
Sanford Natural gas Volusia 2.4 GW 7.5 TWh 36% 1969
H L Culbreath Bayside Power Station Natural gas Hillsborough 2.3 GW 5.8 TWh 29% 1965
Hines Energy Complex Natural gas Polk 2.3 GW 12 TWh 59% 1999
St Lucie Nuclear St. Lucie 2.2 GW 16 TWh 87% 1976
Gulf Clean Energy Center Natural gas Escambia 2.1 GW 2.0 TWh 11% 1959
Seminole (FL) Natural gas Putnam 1.9 GW 10 TWh 61% 1984
Big Bend Natural gas Hillsborough 1.8 GW 7.5 TWh 48% 1970
Okeechobee Clean Energy Center Natural gas Okeechobee 1.7 GW 12 TWh 79% 2019
P L Bartow Natural gas Pinellas 1.5 GW 6.0 TWh 46% 1972
Polk Natural gas Polk 1.5 GW 4.3 TWh 34% 1996
Dania Beach 7 Natural gas Broward 1.4 GW 6.1 TWh 48% 2022
Northside Generating Station Coal Duval 1.4 GW 2.9 TWh 23% 1966
Port Everglades Natural gas Broward 1.4 GW 4.5 TWh 38% 2016
Cape Canaveral Natural gas Brevard 1.3 GW 7.0 TWh 61% 2013

Coming next

Planned projects

The largest generators reported as planned in Florida, by expected year. Plans change; some will be delayed or cancelled.

ProjectSourceCountyCapacityExpected
Shady Hills Combined Cycle Facility Natural gas Pasco 612 MW 2026
Powerline Energy Storage Storage Citrus 100 MW 2027
Big Bend III Battery Storage Storage Hillsborough 75 MW 2028
Caverns Solar Solar Jackson 75 MW 2029
Turnpike Solar Plant Solar Osceola 75 MW 2027
Lonesome Camp Solar Plant Solar Osceola 75 MW 2027
Highland Solar North Solar Highlands 75 MW 2027
Keene Branch Solar Solar Hillsborough 75 MW 2026
FRP Miller Solar Solar Duval 75 MW 2026
Tangelo Solar Okeechobee 75 MW 2027
Hendry Solar Hendry 75 MW 2027
Middle Lake Solar Madison 75 MW 2027

Shut down

Retired since 2010

The largest generators retired in Florida since 2010.

PlantSourceCapacityRetired
Martin Oil 935 MW 2018
Martin Oil 935 MW 2018
Crystal River Nuclear 890 MW 2013
Seminole (FL) Coal 715 MW 2024
St Johns River Power Park Coal 679 MW 2018
St Johns River Power Park Coal 679 MW 2018
Crystal River Coal 524 MW 2018
Big Bend Natural gas 446 MW 2023
Big Bend Coal 446 MW 2021
Crystal River Coal 441 MW 2018
Cape Canaveral Oil 402 MW 2010
Cape Canaveral Oil 402 MW 2010

Sources: U.S. Energy Information Administration: state historical generation tables (1990–2025), Form EIA-860M generator inventory (September 2026) and Form EIA-923 plant generation. Shares leave out pumped storage. Rooftop solar is not included. Methodology.