Solar power plant · Polk, FL

Durrance

Durrance is a 60 MW solar power plant in Polk County, Florida, operated by Tampa Electric Co. Its oldest generator still running came online in 2021. In 2025 it generated 50 GWh, about what 3,800 average Florida homes use in a year.

Capacity60 MWNameplate, September 2026
Generated50 GWhIn 2025
Capacity factor10%Share of the most it could make, 2025
Generators1Oldest from 2021

Durrance in context

Among the 226 solar plants in Florida in the EIA's inventory, it is the 171st largest, about 0.4% of the state's 14 GW of solar capacity.

Polk County has 29 power plants of 1 MW or more with 6.7 GW in all; Durrance is 1% of that and the 6th largest of 15 solar plants there.

Its capacity factor of 10% in 2025 is lower than the 20% typical for solar plants across the US.

The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02040608010012020212022202320242025GWh 50
0204060801001202021202220232024202550

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Durrance (outlined) and other plants in Polk County, shaded. 27.780, -81.980.

Plant facts

Operator
Tampa Electric Co
Sector
Electric Utility
Grid operator
TEC
County
Polk County, FL
EIA plant ID
63495
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 60 MW 2021 –

Questions

Durrance, answered

How much power does Durrance produce?

Durrance has 60 MW of capacity from one generator. In 2025 it generated 50 GWh, 10% of the most it could have made running flat out all year (its capacity factor).

How many homes does Durrance power?

Its 2025 output of 50 GWh equals the yearly electricity use of about 3,800 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Durrance?

Durrance is in Polk County, Florida, at about 27.780°, -81.980°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.

Who operates Durrance?

It is operated by Tampa Electric Co (EIA sector: Electric Utility), and it feeds balancing authority TEC.

When did Durrance open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.