Hendry Isles is a 75 MW solar power plant in Hendry County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2024. In 2025 it generated 173 GWh, about what 13,000 average Florida homes use in a year.

Capacity75 MWNameplate, September 2026
Generated173 GWhIn 2025
Capacity factor27%Share of the most it could make, 2025
Generators1Oldest from 2024

Hendry Isles in context

Among the 226 solar plants in Florida in the EIA's inventory, it is the 128th largest, about 0.5% of the state's 14 GW of solar capacity.

Hendry County has 10 power plants of 1 MW or more with 720 MW in all; Hendry Isles is 10% of that and the 8th largest of 9 solar plants there.

Its capacity factor of 27% in 2025 is higher than the 20% typical for solar plants across the US.

The average electricity customer in Hendry County goes 6.1 hours a year without power, the 44th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05010015020020242025GWh 173
05010015020020242025173

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Hendry Isles (outlined) and other plants in Hendry County, shaded. 26.749, -81.192.

Plant facts

Operator
Florida Power & Light Co
Sector
Electric Utility
Grid operator
FPL
County
Hendry County, FL
EIA plant ID
65909
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 75 MW 2024 –

Questions

Hendry Isles, answered

How much power does Hendry Isles produce?

Hendry Isles has 75 MW of capacity from one generator. In 2025 it generated 173 GWh, 27% of the most it could have made running flat out all year (its capacity factor).

How many homes does Hendry Isles power?

Its 2025 output of 173 GWh equals the yearly electricity use of about 13,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Hendry Isles?

Hendry Isles is in Hendry County, Florida, at about 26.749°, -81.192°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Hendry County goes 6.1 hours a year without power, the 44th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Hendry Isles?

It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.

When did Hendry Isles open?

Its oldest generator still running came online in 2024.