Natural gas power plant · Putnam, FL

Seminole (FL)

Seminole (FL) is a 1.9 GW natural gas power plant in Putnam County, Florida, operated by Seminole Electric Cooperative Inc. Its oldest generator still running came online in 1984. In 2025 it generated 10 TWh, about what 771,000 average Florida homes use in a year.

Capacity1.9 GWNameplate, September 2026
Generated10 TWhIn 2025
Capacity factor61%Share of the most it could make, 2025
Generators4Oldest from 1984

Seminole (FL) in context

Among the 68 natural gas plants in Florida in the EIA's inventory, it is the 10th largest, about 3.4% of the state's 56 GW of natural gas capacity.

Putnam County has 9 power plants of 1 MW or more with 2.5 GW in all; Seminole (FL) is 76% of that.

Its capacity factor of 61% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Putnam County goes 5.5 hours a year without power, the 45th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,0008,00010,00012,00020182019202020212022202320242025GWh 10,206
02,0004,0006,0008,00010,00012,000201920212023202510,206

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Seminole (FL) (outlined) and other plants in Putnam County, shaded. 29.733, -81.633.

Plant facts

Operator
Seminole Electric Cooperative Inc
Sector
Electric Utility
Grid operator
SEC
County
Putnam County, FL
EIA plant ID
136
  • Natural gas1.2 GW62%
  • Coal715 MW38%
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
2 Conventional Steam Coal 715 MW 1984 –
ST Natural Gas Fired Combined Cycle 415 MW 2023 –
CT1 Natural Gas Fired Combined Cycle 384 MW 2023 –
CT2 Natural Gas Fired Combined Cycle 384 MW 2023 –

Retired

GeneratorTechnologyCapacityOnlineRetired
1Conventional Steam Coal715 MW19842024

Questions

Seminole (FL), answered

How much power does Seminole (FL) produce?

Seminole (FL) has 1.9 GW of capacity from 4 generators. In 2025 it generated 10 TWh, 61% of the most it could have made running flat out all year (its capacity factor).

How many homes does Seminole (FL) power?

Its 2025 output of 10 TWh equals the yearly electricity use of about 771,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Seminole (FL)?

Seminole (FL) is in Putnam County, Florida, at about 29.733°, -81.633°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Putnam County goes 5.5 hours a year without power, the 45th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Seminole (FL)?

It is operated by Seminole Electric Cooperative Inc (EIA sector: Electric Utility), and it feeds balancing authority SEC.

When did Seminole (FL) open?

Its oldest generator still running came online in 1984.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.