Solar power plant · Putnam, FL

Twin Lakes

Twin Lakes is a 75 MW solar power plant in Putnam County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2020. In 2025 it generated 123 GWh, about what 9,300 average Florida homes use in a year.

Capacity75 MWNameplate, September 2026
Generated123 GWhIn 2025
Capacity factor19%Share of the most it could make, 2025
Generators1Oldest from 2020

Twin Lakes in context

Among the 226 solar plants in Florida in the EIA's inventory, it is the 59th largest, about 0.5% of the state's 14 GW of solar capacity.

Putnam County has 9 power plants of 1 MW or more with 2.5 GW in all; Twin Lakes is 3% of that and the 4th largest of 7 solar plants there.

Its capacity factor of 19% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Putnam County goes 5.5 hours a year without power, the 45th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

050100150200202020212022202320242025GWh 123
050100150200202020212022202320242025123

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Twin Lakes (outlined) and other plants in Putnam County, shaded. 29.612, -81.845.

Plant facts

Operator
Florida Power & Light Co
Sector
Electric Utility
Grid operator
FPL
County
Putnam County, FL
EIA plant ID
62633
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 75 MW 2020 –

Questions

Twin Lakes, answered

How much power does Twin Lakes produce?

Twin Lakes has 75 MW of capacity from one generator. In 2025 it generated 123 GWh, 19% of the most it could have made running flat out all year (its capacity factor).

How many homes does Twin Lakes power?

Its 2025 output of 123 GWh equals the yearly electricity use of about 9,300 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Twin Lakes?

Twin Lakes is in Putnam County, Florida, at about 29.612°, -81.845°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Putnam County goes 5.5 hours a year without power, the 45th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Twin Lakes?

It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.

When did Twin Lakes open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.