Solar power plant · Hillsborough, FL

Laurel Oaks Solar

Laurel Oaks Solar is a 61 MW solar power plant in Hillsborough County, Florida, operated by Tampa Electric Co. Its oldest generator still running came online in 2022. In 2025 it generated 124 GWh, about what 9,400 average Florida homes use in a year.

Capacity61 MWNameplate, September 2026
Generated124 GWhIn 2025
Capacity factor23%Share of the most it could make, 2025
Generators1Oldest from 2022

Laurel Oaks Solar in context

Among the 226 solar plants in Florida in the EIA's inventory, it is the 168th largest, about 0.4% of the state's 14 GW of solar capacity.

Hillsborough County has 25 power plants of 1 MW or more with 5.1 GW in all; Laurel Oaks Solar is 1% of that and the 7th largest of 17 solar plants there.

Its capacity factor of 23% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Hillsborough County goes 6.6 hours a year without power, the 42nd most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

0501001502022202320242025GWh 124
0501001502022202320242025124

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Laurel Oaks Solar (outlined) and other plants in Hillsborough County, shaded. 27.927, -82.068.

Plant facts

Operator
Tampa Electric Co
Sector
Electric Utility
Grid operator
TEC
County
Hillsborough County, FL
EIA plant ID
65684
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 61 MW 2022 –

Questions

Laurel Oaks Solar, answered

How much power does Laurel Oaks Solar produce?

Laurel Oaks Solar has 61 MW of capacity from one generator. In 2025 it generated 124 GWh, 23% of the most it could have made running flat out all year (its capacity factor).

How many homes does Laurel Oaks Solar power?

Its 2025 output of 124 GWh equals the yearly electricity use of about 9,400 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Laurel Oaks Solar?

Laurel Oaks Solar is in Hillsborough County, Florida, at about 27.927°, -82.068°. It is one of 25 power plants of 1 MW or more in the county. The average electricity customer in Hillsborough County goes 6.6 hours a year without power, the 42nd most of 67 counties in Florida. The county's page has the full outage record.

Who operates Laurel Oaks Solar?

It is operated by Tampa Electric Co (EIA sector: Electric Utility), and it feeds balancing authority TEC.

When did Laurel Oaks Solar open?

Its oldest generator still running came online in 2022.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2022–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.