Natural gas power plant · Hillsborough, FL

South Tampa Resilience Project

South Tampa Resilience Project is a 75 MW natural gas power plant in Hillsborough County, Florida, operated by Tampa Electric Co. Its oldest generator still running came online in 2025. In 2025 it generated 23 GWh, about what 1,700 average Florida homes use in a year.

Capacity75 MWNameplate, September 2026
Generated23 GWhIn 2025
Capacity factor–Not a full year of data
Generators4Oldest from 2025

South Tampa Resilience Project in context

Among the 68 natural gas plants in Florida in the EIA's inventory, it is the 52nd largest, about 0.1% of the state's 56 GW of natural gas capacity.

Hillsborough County has 25 power plants of 1 MW or more with 5.1 GW in all; South Tampa Resilience Project is 1% of that and the 3rd largest of 3 natural gas plants there.

The average electricity customer in Hillsborough County goes 6.6 hours a year without power, the 42nd most of 67 counties in Florida. The county's page has the full outage record.

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

South Tampa Resilience Project (outlined) and other plants in Hillsborough County, shaded. 27.863, -82.517.

Plant facts

Operator
Tampa Electric Co
Sector
Electric Utility
Grid operator
TEC
County
Hillsborough County, FL
EIA plant ID
66920
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
MPS01 Natural Gas Internal Combustion Engine 19 MW 2025 –
MPS02 Natural Gas Internal Combustion Engine 19 MW 2025 –
MPS03 Natural Gas Internal Combustion Engine 19 MW 2025 –
MPS04 Natural Gas Internal Combustion Engine 19 MW 2025 –

Questions

South Tampa Resilience Project, answered

How much power does South Tampa Resilience Project produce?

South Tampa Resilience Project has 75 MW of capacity from 4 generators. In 2025 it generated 23 GWh.

How many homes does South Tampa Resilience Project power?

Its 2025 output of 23 GWh equals the yearly electricity use of about 1,700 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is South Tampa Resilience Project?

South Tampa Resilience Project is in Hillsborough County, Florida, at about 27.863°, -82.517°. It is one of 25 power plants of 1 MW or more in the county. The average electricity customer in Hillsborough County goes 6.6 hours a year without power, the 42nd most of 67 counties in Florida. The county's page has the full outage record.

Who operates South Tampa Resilience Project?

It is operated by Tampa Electric Co (EIA sector: Electric Utility), and it feeds balancing authority TEC.

When did South Tampa Resilience Project open?

Its oldest generator still running came online in 2025.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.