Solar power plant · DeSoto, FL
Rodeo Solar Center
Rodeo Solar Center is a 75 MW solar power plant in DeSoto County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2021. In 2025 it generated 145 GWh, about what 11,000 average Florida homes use in a year.
Rodeo Solar Center in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 66th largest, about 0.5% of the state's 14 GW of solar capacity.
DeSoto County has 9 power plants of 1 MW or more with 625 MW in all; Rodeo Solar Center is 12% of that and the 4th largest of 9 solar plants there.
Its capacity factor of 22% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in DeSoto County goes 16 hours a year without power, the 24th most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Rodeo Solar Center (outlined) and other plants in DeSoto County, shaded. 27.321, -81.810.
Plant facts
- Operator
- Florida Power & Light Co
- Sector
- Electric Utility
- Grid operator
- FPL
- County
- DeSoto County, FL
- EIA plant ID
- 62917
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 75 MW | 2021 | – |
Questions
Rodeo Solar Center, answered
How much power does Rodeo Solar Center produce?
Rodeo Solar Center has 75 MW of capacity from one generator. In 2025 it generated 145 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Rodeo Solar Center power?
Its 2025 output of 145 GWh equals the yearly electricity use of about 11,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Rodeo Solar Center?
Rodeo Solar Center is in DeSoto County, Florida, at about 27.321°, -81.810°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in DeSoto County goes 16 hours a year without power, the 24th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Rodeo Solar Center?
It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.
When did Rodeo Solar Center open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.