Solar power plant · DeSoto, FL
Citrus Solar Energy Center Hybrid
Citrus Solar Energy Center Hybrid is a 79 MW solar power plant in DeSoto County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2016. In 2025 it generated 138 GWh, about what 10,000 average Florida homes use in a year.
Citrus Solar Energy Center Hybrid in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 13th largest, about 0.6% of the state's 14 GW of solar capacity.
DeSoto County has 9 power plants of 1 MW or more with 625 MW in all; Citrus Solar Energy Center Hybrid is 13% of that and the largest of 9 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in DeSoto County goes 16 hours a year without power, the 24th most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Citrus Solar Energy Center Hybrid (outlined) and other plants in DeSoto County, shaded. 27.321, -81.807.
Plant facts
- Operator
- Florida Power & Light Co
- Sector
- Electric Utility
- Grid operator
- FPL
- County
- DeSoto County, FL
- EIA plant ID
- 60061
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 75 MW | 2016 | – |
| BA | Batteries | 4.0 MW · 16 MWh | 2018 | – |
Questions
Citrus Solar Energy Center Hybrid, answered
How much power does Citrus Solar Energy Center Hybrid produce?
Citrus Solar Energy Center Hybrid has 79 MW of capacity from 2 generators. In 2025 it generated 138 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Citrus Solar Energy Center Hybrid power?
Its 2025 output of 138 GWh equals the yearly electricity use of about 10,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Citrus Solar Energy Center Hybrid?
Citrus Solar Energy Center Hybrid is in DeSoto County, Florida, at about 27.321°, -81.807°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in DeSoto County goes 16 hours a year without power, the 24th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Citrus Solar Energy Center Hybrid?
It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.
When did Citrus Solar Energy Center Hybrid open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.