Other power plant · Polk, FL
Mosaic South Pierce Operations
Mosaic South Pierce Operations is a 38 MW other power plant in Polk County, Florida, operated by Mosaic Fertilizer LLC. Its oldest generator still running came online in 1992. In 2025 it generated 88 GWh, about what 6,600 average Florida homes use in a year.
Mosaic South Pierce Operations in context
Among the 40 other-fuel plants in Florida in the EIA's inventory, it is the 22nd largest, about 1.4% of the state's 2.6 GW of other-fuel capacity.
Polk County has 29 power plants of 1 MW or more with 6.7 GW in all; Mosaic South Pierce Operations is 1% of that and the 4th largest of 4 other plants there.
Its capacity factor of 26% in 2025 is close to the 25% typical for other plants across the US.
The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Mosaic South Pierce Operations (outlined) and other plants in Polk County, shaded. 27.765, -81.939.
Plant facts
- Operator
- Mosaic Fertilizer LLC
- Sector
- Industrial CHP
- Grid operator
- TEC
- County
- Polk County, FL
- EIA plant ID
- 10004
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| TG2 | All Other | 38 MW | 1992 | – |
Retired
| Generator | Technology | Capacity | Online | Retired |
|---|---|---|---|---|
| TG1 | All Other | 7.5 MW | 1978 | 2025 |
Questions
Mosaic South Pierce Operations, answered
How much power does Mosaic South Pierce Operations produce?
Mosaic South Pierce Operations has 38 MW of capacity from one generator. In 2025 it generated 88 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Mosaic South Pierce Operations power?
Its 2025 output of 88 GWh equals the yearly electricity use of about 6,600 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Mosaic South Pierce Operations?
Mosaic South Pierce Operations is in Polk County, Florida, at about 27.765°, -81.939°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Who operates Mosaic South Pierce Operations?
It is operated by Mosaic Fertilizer LLC (EIA sector: Industrial CHP), and it feeds balancing authority TEC.
When did Mosaic South Pierce Operations open?
Its oldest generator still running came online in 1992.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.