Biomass power plant · Lake, FL

Covanta Lake County Energy

Covanta Lake County Energy is a 16 MW biomass power plant in Lake County, Florida, operated by Covanta Lake Inc. Its oldest generator still running came online in 1990. In 2025 it generated 87 GWh, about what 6,600 average Florida homes use in a year.

Capacity16 MWNameplate, September 2026
Generated87 GWhIn 2025
Capacity factor64%Share of the most it could make, 2025
Generators1Oldest from 1990

Covanta Lake County Energy in context

Among the 40 other-fuel plants in Florida in the EIA's inventory, it is the 26th largest, about 0.6% of the state's 2.6 GW of other-fuel capacity.

Lake County has 4 power plants of 1 MW or more with 24 MW in all; Covanta Lake County Energy is 66% of that.

Its capacity factor of 64% in 2025 is higher than the 25% typical for biomass plants across the US.

The average electricity customer in Lake County goes 5.4 hours a year without power, the 46th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02040608010020182019202020212022202320242025GWh 87
020406080100201920212023202587

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Covanta Lake County Energy (outlined) and other plants in Lake County, shaded. 28.740, -81.889.

Plant facts

Operator
Covanta Lake Inc
Sector
IPP Non-CHP
Grid operator
FPC
County
Lake County, FL
EIA plant ID
50629
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Municipal Solid Waste 16 MW 1990 –

Nearby

Other plants in Lake County

Cutrale Citrus Juices USA I · 4.1 MWMount Dora Solar Farm F · 2.1 MWMount Dora Solar Farm W · 1.9 MW

Questions

Covanta Lake County Energy, answered

How much power does Covanta Lake County Energy produce?

Covanta Lake County Energy has 16 MW of capacity from one generator. In 2025 it generated 87 GWh, 64% of the most it could have made running flat out all year (its capacity factor).

How many homes does Covanta Lake County Energy power?

Its 2025 output of 87 GWh equals the yearly electricity use of about 6,600 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Covanta Lake County Energy?

Covanta Lake County Energy is in Lake County, Florida, at about 28.740°, -81.889°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Lake County goes 5.4 hours a year without power, the 46th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Covanta Lake County Energy?

It is operated by Covanta Lake Inc (EIA sector: IPP Non-CHP), and it feeds balancing authority FPC.

When did Covanta Lake County Energy open?

Its oldest generator still running came online in 1990.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.