Solar power plant · Polk, FL
Bonnie Mine Solar
Bonnie Mine Solar is a 38 MW solar power plant in Polk County, Florida, operated by Tampa Electric Co. Its oldest generator still running came online in 2019. In 2025 it generated 67 GWh, about what 5,000 average Florida homes use in a year.
Bonnie Mine Solar in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 182nd largest, about 0.3% of the state's 14 GW of solar capacity.
Polk County has 29 power plants of 1 MW or more with 6.7 GW in all; Bonnie Mine Solar is 1% of that and the 9th largest of 15 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Bonnie Mine Solar (outlined) and other plants in Polk County, shaded. 27.890, -81.987.
Plant facts
- Operator
- Tampa Electric Co
- Sector
- Electric Utility
- Grid operator
- TEC
- County
- Polk County, FL
- EIA plant ID
- 61655
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 38 MW | 2019 | – |
Questions
Bonnie Mine Solar, answered
How much power does Bonnie Mine Solar produce?
Bonnie Mine Solar has 38 MW of capacity from one generator. In 2025 it generated 67 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Bonnie Mine Solar power?
Its 2025 output of 67 GWh equals the yearly electricity use of about 5,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Bonnie Mine Solar?
Bonnie Mine Solar is in Polk County, Florida, at about 27.890°, -81.987°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Who operates Bonnie Mine Solar?
It is operated by Tampa Electric Co (EIA sector: Electric Utility), and it feeds balancing authority TEC.
When did Bonnie Mine Solar open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.