Storage power plant · Gilchrist, FL

Trenton

Trenton is a 11 MW storage power plant in Gilchrist County, Florida, operated by Duke Energy Florida, LLC. Its oldest generator still running came online in 2021.

Capacity11 MWNameplate, September 2026
Net energy-0.1 GWhIn 2025
Capacity factor–Not a full year of data
Generators1Oldest from 2021

Trenton in context

Among the 9 storage plants in Florida in the EIA's inventory, it is the 3rd largest, about 2.0% of the state's 552 MW of storage capacity.

Gilchrist County has 4 power plants of 1 MW or more with 235 MW in all; Trenton is 5% of that.

The average electricity customer in Gilchrist County goes 19 hours a year without power, the 16th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.

000111120242025GWh -0
000111120242025-0

Where it is

Trenton (outlined) and other plants in Gilchrist County, shaded. 29.614, -82.807.

Plant facts

Operator
Duke Energy Florida, LLC
Sector
Electric Utility
Grid operator
FPC
County
Gilchrist County, FL
EIA plant ID
63995
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ES1 Batteries 11 MW · 10 MWh 2021 –

Questions

Trenton, answered

How much can Trenton store and deliver?

Trenton can deliver up to 11 MW and hold 10 MWh of energy, from one battery or storage system. Its net energy in 2025 was -0.1 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.

Where is Trenton?

Trenton is in Gilchrist County, Florida, at about 29.614°, -82.807°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Gilchrist County goes 19 hours a year without power, the 16th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Trenton?

It is operated by Duke Energy Florida, LLC (EIA sector: Electric Utility), and it feeds balancing authority FPC.

When did Trenton open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.