Biomass power plant · Broward, FL

CSL Gas Recovery

CSL Gas Recovery is a 11 MW biomass power plant in Broward County, Florida, operated by WM Renewable Energy LLC. Its oldest generator still running came online in 1989. In 2025 it generated 40 GWh, about what 3,000 average Florida homes use in a year.

Capacity11 MWNameplate, September 2026
Generated40 GWhIn 2025
Capacity factor41%Share of the most it could make, 2025
Generators4Oldest from 1989

CSL Gas Recovery in context

Among the 40 other-fuel plants in Florida in the EIA's inventory, it is the 27th largest, about 0.4% of the state's 2.6 GW of other-fuel capacity.

Broward County has 6 power plants of 1 MW or more with 4.1 GW in all; CSL Gas Recovery is 0% of that and the 2nd largest of 2 biomass plants there.

Its capacity factor of 41% in 2025 is higher than the 25% typical for biomass plants across the US.

The average electricity customer in Broward County goes 1.4 hours a year without power, the 67th most of 67 counties in Florida. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020406020182019202020212022202320242025GWh 40
0204060201920212023202540

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

CSL Gas Recovery (outlined) and other plants in Broward County, shaded. 26.288, -80.167.

Plant facts

Operator
WM Renewable Energy LLC
Sector
IPP Non-CHP
Grid operator
FPL
County
Broward County, FL
EIA plant ID
50572
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Landfill Gas 3.0 MW 1989 –
GEN2 Landfill Gas 3.0 MW 1989 –
GEN3 Landfill Gas 3.0 MW 1989 –
GEN4 Landfill Gas 2.2 MW 2000 –

Nearby

Other plants in Broward County

Questions

CSL Gas Recovery, answered

How much power does CSL Gas Recovery produce?

CSL Gas Recovery has 11 MW of capacity from 4 generators. In 2025 it generated 40 GWh, 41% of the most it could have made running flat out all year (its capacity factor).

How many homes does CSL Gas Recovery power?

Its 2025 output of 40 GWh equals the yearly electricity use of about 3,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is CSL Gas Recovery?

CSL Gas Recovery is in Broward County, Florida, at about 26.288°, -80.167°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Broward County goes 1.4 hours a year without power, the 67th most of 67 counties in Florida. The county's page has the full outage record.

Who operates CSL Gas Recovery?

It is operated by WM Renewable Energy LLC (EIA sector: IPP Non-CHP), and it feeds Florida Power & Light.

When did CSL Gas Recovery open?

Its oldest generator still running came online in 1989.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.