Solar power plant · Indian River, FL
Turnpike
Turnpike is a 75 MW solar power plant in Indian River County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2024. In 2025 it generated 171 GWh, about what 13,000 average Florida homes use in a year.
Turnpike in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 114th largest, about 0.5% of the state's 14 GW of solar capacity.
Indian River County has 5 power plants of 1 MW or more with 373 MW in all; Turnpike is 20% of that and the 5th largest of 5 solar plants there.
Its capacity factor of 26% in 2025 is higher than the 20% typical for solar plants across the US.
The average electricity customer in Indian River County goes 9.6 hours a year without power, the 34th most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Turnpike (outlined) and other plants in Indian River County, shaded. 27.567, -80.645.
Plant facts
- Operator
- Florida Power & Light Co
- Sector
- Electric Utility
- Grid operator
- FPL
- County
- Indian River County, FL
- EIA plant ID
- 65873
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 75 MW | 2024 | – |
Nearby
Other plants in Indian River County
Questions
Turnpike, answered
How much power does Turnpike produce?
Turnpike has 75 MW of capacity from one generator. In 2025 it generated 171 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Turnpike power?
Its 2025 output of 171 GWh equals the yearly electricity use of about 13,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Turnpike?
Turnpike is in Indian River County, Florida, at about 27.567°, -80.645°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Indian River County goes 9.6 hours a year without power, the 34th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Turnpike?
It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.
When did Turnpike open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.