Other power plant · Polk, FL
Mosaic Co Bartow Facility
Mosaic Co Bartow Facility is a 82 MW other power plant in Polk County, Florida, operated by Mosaic Company. Its oldest generator still running came online in 1985. In 2025 it generated 171 GWh, about what 13,000 average Florida homes use in a year.
Mosaic Co Bartow Facility in context
Among the 40 other-fuel plants in Florida in the EIA's inventory, it is the 10th largest, about 3.1% of the state's 2.6 GW of other-fuel capacity.
Polk County has 29 power plants of 1 MW or more with 6.7 GW in all; Mosaic Co Bartow Facility is 1% of that and the 2nd largest of 4 other plants there.
Its capacity factor of 24% in 2025 is close to the 25% typical for other plants across the US.
The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Mosaic Co Bartow Facility (outlined) and other plants in Polk County, shaded. 27.908, -81.918.
Plant facts
- Operator
- Mosaic Company
- Sector
- Industrial CHP
- Grid operator
- TEC
- County
- Polk County, FL
- EIA plant ID
- 50633
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN2 | All Other | 45 MW | 1992 | – |
| GEN1 | All Other | 37 MW | 1985 | – |
Questions
Mosaic Co Bartow Facility, answered
How much power does Mosaic Co Bartow Facility produce?
Mosaic Co Bartow Facility has 82 MW of capacity from 2 generators. In 2025 it generated 171 GWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Mosaic Co Bartow Facility power?
Its 2025 output of 171 GWh equals the yearly electricity use of about 13,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Mosaic Co Bartow Facility?
Mosaic Co Bartow Facility is in Polk County, Florida, at about 27.908°, -81.918°. It is one of 29 power plants of 1 MW or more in the county. The average electricity customer in Polk County goes 9.9 hours a year without power, the 33rd most of 67 counties in Florida. The county's page has the full outage record.
Who operates Mosaic Co Bartow Facility?
It is operated by Mosaic Company (EIA sector: Industrial CHP), and it feeds balancing authority TEC.
When did Mosaic Co Bartow Facility open?
Its oldest generator still running came online in 1985.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.