Indian River is a 609 MW natural gas power plant in Brevard County, Florida, operated by Orlando Utilities Comm. Its oldest generator still running came online in 1960.
Indian River in context
Among the 68 natural gas plants in Florida in the EIA's inventory, it is the 32nd largest, about 1.1% of the state's 56 GW of natural gas capacity.
Brevard County has 12 power plants of 1 MW or more with 3.7 GW in all; Indian River is 16% of that and the 3rd largest of 4 natural gas plants there.
The average electricity customer in Brevard County goes 4.7 hours a year without power, the 51st most of 67 counties in Florida. The county's page has the full outage record.
Where it is
Indian River (outlined) and other plants in Brevard County, shaded. 28.493, -80.780.
Plant facts
- Operator
- Orlando Utilities Comm
- Sector
- Electric Utility
- Grid operator
- FMPP
- County
- Brevard County, FL
- EIA plant ID
- 55318
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 3 | Natural Gas Steam Turbine | 317 MW | 1974 | – |
| 2 | Natural Gas Steam Turbine | 213 MW | 1964 | – |
| 1 | Natural Gas Steam Turbine | 79 MW | 1960 | – |
Questions
Indian River, answered
How much power does Indian River produce?
Indian River has 609 MW of capacity from 3 generators. No full year of generation is reported yet.
Where is Indian River?
Indian River is in Brevard County, Florida, at about 28.493°, -80.780°. It is one of 12 power plants of 1 MW or more in the county. The average electricity customer in Brevard County goes 4.7 hours a year without power, the 51st most of 67 counties in Florida. The county's page has the full outage record.
Who operates Indian River?
It is operated by Orlando Utilities Comm (EIA sector: Electric Utility), and it feeds balancing authority FMPP.
When did Indian River open?
Its oldest generator still running came online in 1960.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.