Solar power plant · Walton, FL
Swallowtail
Swallowtail is a 75 MW solar power plant in Walton County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2025. In 2025 it generated 170 GWh, about what 13,000 average Florida homes use in a year.
Swallowtail in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 153rd largest, about 0.5% of the state's 14 GW of solar capacity.
Walton County has 4 power plants of 1 MW or more with 298 MW in all; Swallowtail is 25% of that and the 4th largest of 4 solar plants there.
The average electricity customer in Walton County goes 3.1 hours a year without power, the 59th most of 67 counties in Florida. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Swallowtail (outlined) and other plants in Walton County, shaded. 30.924, -86.231.
Plant facts
- Operator
- Florida Power & Light Co
- Sector
- Electric Utility
- Grid operator
- FPL
- County
- Walton County, FL
- EIA plant ID
- 67673
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 75 MW | 2025 | – |
Nearby
Other plants in Walton County
Questions
Swallowtail, answered
How much power does Swallowtail produce?
Swallowtail has 75 MW of capacity from one generator. In 2025 it generated 170 GWh.
How many homes does Swallowtail power?
Its 2025 output of 170 GWh equals the yearly electricity use of about 13,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Swallowtail?
Swallowtail is in Walton County, Florida, at about 30.924°, -86.231°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Walton County goes 3.1 hours a year without power, the 59th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Swallowtail?
It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.
When did Swallowtail open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.