Tenmile Creek is a 149 MW solar power plant in Calhoun County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2025. In 2025 it generated 182 GWh, about what 14,000 average Florida homes use in a year.

Capacity149 MWNameplate, September 2026
Generated182 GWhIn 2025
Capacity factor–Not a full year of data
Generators2Oldest from 2025

Tenmile Creek in context

Among the 226 solar plants in Florida in the EIA's inventory, it is the 5th largest, about 1.1% of the state's 14 GW of solar capacity.

Calhoun County has 7 power plants of 1 MW or more with 820 MW in all; Tenmile Creek is 18% of that and the 3rd largest of 7 solar plants there.

The average electricity customer in Calhoun County goes 18 hours a year without power, the 17th most of 67 counties in Florida. The county's page has the full outage record.

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Tenmile Creek (outlined) and other plants in Calhoun County, shaded. 30.504, -85.167.

Plant facts

Operator
Florida Power & Light Co
Sector
Electric Utility
Grid operator
FPL
County
Calhoun County, FL
EIA plant ID
65886
  • Solar75 MW50%
  • Storage75 MW50%
Where Florida's power comes from → Florida power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Solar Photovoltaic 75 MW 2025 –
2 Batteries 75 MW · 224 MWh 2025 –

Questions

Tenmile Creek, answered

How much power does Tenmile Creek produce?

Tenmile Creek has 149 MW of capacity from 2 generators. In 2025 it generated 182 GWh.

How many homes does Tenmile Creek power?

Its 2025 output of 182 GWh equals the yearly electricity use of about 14,000 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Tenmile Creek?

Tenmile Creek is in Calhoun County, Florida, at about 30.504°, -85.167°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Calhoun County goes 18 hours a year without power, the 17th most of 67 counties in Florida. The county's page has the full outage record.

Who operates Tenmile Creek?

It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.

When did Tenmile Creek open?

Its oldest generator still running came online in 2025.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.