Solar power plant · St. Lucie, FL
North Orange
North Orange is a 75 MW solar power plant in St. Lucie County, Florida, operated by Florida Power & Light Co. Its oldest generator still running came online in 2026.
North Orange in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 121st largest, about 0.5% of the state's 14 GW of solar capacity.
St. Lucie County has 14 power plants of 1 MW or more with 3.5 GW in all; North Orange is 2% of that and the 8th largest of 12 solar plants there.
The average electricity customer in St. Lucie County goes 2.7 hours a year without power, the 62nd most of 67 counties in Florida. The county's page has the full outage record.
Where it is
North Orange (outlined) and other plants in St. Lucie County, shaded. 27.514, -80.571.
Plant facts
- Operator
- Florida Power & Light Co
- Sector
- Electric Utility
- Grid operator
- FPL
- County
- St. Lucie County, FL
- EIA plant ID
- 65883
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Solar Photovoltaic | 75 MW | 2026 | – |
Questions
North Orange, answered
How much power does North Orange produce?
North Orange has 75 MW of capacity from one generator. No full year of generation is reported yet.
Where is North Orange?
North Orange is in St. Lucie County, Florida, at about 27.514°, -80.571°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in St. Lucie County goes 2.7 hours a year without power, the 62nd most of 67 counties in Florida. The county's page has the full outage record.
Who operates North Orange?
It is operated by Florida Power & Light Co (EIA sector: Electric Utility), and it feeds Florida Power & Light.
When did North Orange open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.