Solar power plant · Orange, FL
Citrus Ridge Solar
Citrus Ridge Solar is a 52 MW solar power plant in Orange County, Florida, operated by FL Solar 5, LLC. Its oldest generator still running came online in 2018. In 2025 it generated 95 GWh, about what 7,200 average Florida homes use in a year.
Citrus Ridge Solar in context
Among the 226 solar plants in Florida in the EIA's inventory, it is the 175th largest, about 0.4% of the state's 14 GW of solar capacity.
Orange County has 10 power plants of 1 MW or more with 2.2 GW in all; Citrus Ridge Solar is 2% of that and the 2nd largest of 6 solar plants there.
Its capacity factor of 21% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Orange County goes 6.7 hours a year without power, the 41st most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Citrus Ridge Solar (outlined) and other plants in Orange County, shaded. 28.401, -81.616.
Plant facts
- Operator
- FL Solar 5, LLC
- Sector
- IPP Non-CHP
- Grid operator
- FPC
- County
- Orange County, FL
- EIA plant ID
- 61988
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| FL501 | Solar Photovoltaic | 52 MW | 2018 | – |
Nearby
Other plants in Orange County
Questions
Citrus Ridge Solar, answered
How much power does Citrus Ridge Solar produce?
Citrus Ridge Solar has 52 MW of capacity from one generator. In 2025 it generated 95 GWh, 21% of the most it could have made running flat out all year (its capacity factor).
How many homes does Citrus Ridge Solar power?
Its 2025 output of 95 GWh equals the yearly electricity use of about 7,200 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Citrus Ridge Solar?
Citrus Ridge Solar is in Orange County, Florida, at about 28.401°, -81.616°. It is one of 10 power plants of 1 MW or more in the county. The average electricity customer in Orange County goes 6.7 hours a year without power, the 41st most of 67 counties in Florida. The county's page has the full outage record.
Who operates Citrus Ridge Solar?
It is operated by FL Solar 5, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority FPC.
When did Citrus Ridge Solar open?
Its oldest generator still running came online in 2018.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.