Natural gas power plant · Leon, FL
Sub 12
Sub 12 is a 19 MW natural gas power plant in Leon County, Florida, operated by City of Tallahassee - (FL). Its oldest generator still running came online in 2018. In 2025 it generated 18 GWh, about what 1,400 average Florida homes use in a year.
Sub 12 in context
Among the 68 natural gas plants in Florida in the EIA's inventory, it is the 58th largest, about 0.0% of the state's 56 GW of natural gas capacity.
Leon County has 4 power plants of 1 MW or more with 754 MW in all; Sub 12 is 2% of that and the 2nd largest of 2 natural gas plants there.
Its capacity factor of 11% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Leon County goes 13 hours a year without power, the 28th most of 67 counties in Florida. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Sub 12 (outlined) and other plants in Leon County, shaded. 30.460, -84.260.
Plant facts
- Operator
- City of Tallahassee - (FL)
- Sector
- Electric Utility
- Grid operator
- TAL
- County
- Leon County, FL
- EIA plant ID
- 61080
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| IC1 | Natural Gas Internal Combustion Engine | 9.3 MW | 2018 | – |
| IC2 | Natural Gas Internal Combustion Engine | 9.3 MW | 2018 | – |
Nearby
Other plants in Leon County
Questions
Sub 12, answered
How much power does Sub 12 produce?
Sub 12 has 19 MW of capacity from 2 generators. In 2025 it generated 18 GWh, 11% of the most it could have made running flat out all year (its capacity factor).
How many homes does Sub 12 power?
Its 2025 output of 18 GWh equals the yearly electricity use of about 1,400 average Florida homes (1,103 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Sub 12?
Sub 12 is in Leon County, Florida, at about 30.460°, -84.260°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Leon County goes 13 hours a year without power, the 28th most of 67 counties in Florida. The county's page has the full outage record.
Who operates Sub 12?
It is operated by City of Tallahassee - (FL) (EIA sector: Electric Utility), and it feeds balancing authority TAL.
When did Sub 12 open?
Its oldest generator still running came online in 2018.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Florida home's 1,103 kWh a month in 2025. Methodology.