Wind power plant · Stearns, MN

Black Oak Wind Farm

Black Oak Wind Farm is a 78 MW wind power plant in Stearns County, Minnesota, operated by Black Oak Wind, LLC. Its oldest generator still running came online in 2016. In 2025 it generated 305 GWh, about what 34,000 average Minnesota homes use in a year.

Capacity78 MWNameplate, September 2026
Generated305 GWhIn 2025
Capacity factor45%Share of the most it could make, 2025
Generators1Oldest from 2016

Black Oak Wind Farm in context

Among the 122 wind plants in Minnesota in the EIA's inventory, it is the 27th largest, about 1.6% of the state's 5.0 GW of wind capacity.

Stearns County has 42 power plants of 1 MW or more with 192 MW in all; Black Oak Wind Farm is 41% of that.

Its capacity factor of 45% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Stearns County goes 1.5 hours a year without power, the 46th most of 54 counties in Minnesota. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040020182019202020212022202320242025GWh 305
01002003004002019202120232025305

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Black Oak Wind Farm (outlined) and other plants in Stearns County, shaded. 45.661, -95.013.

Plant facts

Operator
Black Oak Wind, LLC
Sector
IPP Non-CHP
Grid operator
MISO
County
Stearns County, MN
EIA plant ID
58692
Where Minnesota's power comes from → Minnesota power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 78 MW 2016 –

Nearby

Other plants in Stearns County

Albany Solar · 10 MWPaynesville Solar · 10 MWSt. Cloud Hydro · 8.6 MWMelrose · 8.2 MWPaynesville Community Solar · 5.0 MWLahr 1, LLC · 5.0 MWSt. Cloud Solar CSG · 5.0 MWRichmond CSG · 5.0 MW

Questions

Black Oak Wind Farm, answered

How much power does Black Oak Wind Farm produce?

Black Oak Wind Farm has 78 MW of capacity from one generator. In 2025 it generated 305 GWh, 45% of the most it could have made running flat out all year (its capacity factor).

How many homes does Black Oak Wind Farm power?

Its 2025 output of 305 GWh equals the yearly electricity use of about 34,000 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Black Oak Wind Farm?

Black Oak Wind Farm is in Stearns County, Minnesota, at about 45.661°, -95.013°. It is one of 42 power plants of 1 MW or more in the county. The average electricity customer in Stearns County goes 1.5 hours a year without power, the 46th most of 54 counties in Minnesota. The county's page has the full outage record.

Who operates Black Oak Wind Farm?

It is operated by Black Oak Wind, LLC (EIA sector: IPP Non-CHP), and it feeds MISO.

When did Black Oak Wind Farm open?

Its oldest generator still running came online in 2016.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.