Solar power plant · Stearns, MN
Paynesville Solar
Paynesville Solar is a 10 MW solar power plant in Stearns County, Minnesota, operated by Enel Green Power NA, Inc.. Its oldest generator still running came online in 2016. In 2025 it generated 18 GWh, about what 2,000 average Minnesota homes use in a year.
Paynesville Solar in context
Among the 544 solar plants in Minnesota in the EIA's inventory, it is the 13th largest, about 0.5% of the state's 2.1 GW of solar capacity.
Stearns County has 42 power plants of 1 MW or more with 192 MW in all; Paynesville Solar is 5% of that and the 2nd largest of 38 solar plants there.
Its capacity factor of 20% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Stearns County goes 1.5 hours a year without power, the 46th most of 54 counties in Minnesota. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Paynesville Solar (outlined) and other plants in Stearns County, shaded. 45.393, -94.721.
Plant facts
- Operator
- Enel Green Power NA, Inc.
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Stearns County, MN
- EIA plant ID
- 60530
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 10 MW | 2016 | – |
Nearby
Other plants in Stearns County
Questions
Paynesville Solar, answered
How much power does Paynesville Solar produce?
Paynesville Solar has 10 MW of capacity from one generator. In 2025 it generated 18 GWh, 20% of the most it could have made running flat out all year (its capacity factor).
How many homes does Paynesville Solar power?
Its 2025 output of 18 GWh equals the yearly electricity use of about 2,000 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Paynesville Solar?
Paynesville Solar is in Stearns County, Minnesota, at about 45.393°, -94.721°. It is one of 42 power plants of 1 MW or more in the county. The average electricity customer in Stearns County goes 1.5 hours a year without power, the 46th most of 54 counties in Minnesota. The county's page has the full outage record.
Who operates Paynesville Solar?
It is operated by Enel Green Power NA, Inc. (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Paynesville Solar open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.