Solar power plant · Franklin, PA
Blairs Valley Solar Project
Blairs Valley Solar Project is a 20 MW solar power plant in Franklin County, Pennsylvania, operated by CleanChoice Energy. Its oldest generator still running came online in 2025. In 2025 it generated 10 GWh, about what 1,000 average Pennsylvania homes use in a year.
Blairs Valley Solar Project in context
Among the 82 solar plants in Pennsylvania in the EIA's inventory, it is the 24th largest, about 1.6% of the state's 1.2 GW of solar capacity.
Franklin County has 14 power plants of 1 MW or more with 518 MW in all; Blairs Valley Solar Project is 4% of that and the 6th largest of 9 solar plants there.
The average electricity customer in Franklin County goes 2.2 hours a year without power, the 64th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Blairs Valley Solar Project (outlined) and other plants in Franklin County, shaded. 39.803, -77.922.
Plant facts
- Operator
- CleanChoice Energy
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Franklin County, PA
- EIA plant ID
- 69235
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BVCCE | Solar Photovoltaic | 20 MW | 2025 | – |
Questions
Blairs Valley Solar Project, answered
How much power does Blairs Valley Solar Project produce?
Blairs Valley Solar Project has 20 MW of capacity from one generator. In 2025 it generated 10 GWh.
How many homes does Blairs Valley Solar Project power?
Its 2025 output of 10 GWh equals the yearly electricity use of about 1,000 average Pennsylvania homes (839 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Blairs Valley Solar Project?
Blairs Valley Solar Project is in Franklin County, Pennsylvania, at about 39.803°, -77.922°. It is one of 14 power plants of 1 MW or more in the county. The average electricity customer in Franklin County goes 2.2 hours a year without power, the 64th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Who operates Blairs Valley Solar Project?
It is operated by CleanChoice Energy (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Blairs Valley Solar Project open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Pennsylvania home's 839 kWh a month in 2025. Methodology.