Solar power plant · Jefferson, NY
Blanchard Road 1 Community Solar
Blanchard Road 1 Community Solar is a 10 MW solar power plant in Jefferson County, New York, operated by OYA Blanchard Road LLC. Its oldest generator still running came online in 2019. In 2025 it generated 7.1 GWh, about what 1,000 average New York homes use in a year.
Blanchard Road 1 Community Solar in context
Among the 730 solar plants in New York in the EIA's inventory, it is the 22nd largest, about 0.3% of the state's 3.2 GW of solar capacity.
Jefferson County has 33 power plants of 1 MW or more with 256 MW in all; Blanchard Road 1 Community Solar is 4% of that and the largest of 15 solar plants there.
Its capacity factor of 8% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Jefferson County goes 4.7 hours a year without power, the 41st most of 62 counties in New York. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Blanchard Road 1 Community Solar (outlined) and other plants in Jefferson County, shaded. 44.255, -76.012.
Plant facts
- Operator
- OYA Blanchard Road LLC
- Sector
- IPP Non-CHP
- Grid operator
- NYIS
- County
- Jefferson County, NY
- EIA plant ID
- 64084
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BR1CS | Solar Photovoltaic | 5.0 MW | 2019 | – |
| BR1S | Batteries | 5.0 MW · 15 MWh | 2019 | – |
Nearby
Other plants in Jefferson County
Questions
Blanchard Road 1 Community Solar, answered
How much power does Blanchard Road 1 Community Solar produce?
Blanchard Road 1 Community Solar has 10 MW of capacity from 2 generators. In 2025 it generated 7.1 GWh, 8% of the most it could have made running flat out all year (its capacity factor).
How many homes does Blanchard Road 1 Community Solar power?
Its 2025 output of 7.1 GWh equals the yearly electricity use of about 1,000 average New York homes (586 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Blanchard Road 1 Community Solar?
Blanchard Road 1 Community Solar is in Jefferson County, New York, at about 44.255°, -76.012°. It is one of 33 power plants of 1 MW or more in the county. The average electricity customer in Jefferson County goes 4.7 hours a year without power, the 41st most of 62 counties in New York. The county's page has the full outage record.
Who operates Blanchard Road 1 Community Solar?
It is operated by OYA Blanchard Road LLC (EIA sector: IPP Non-CHP), and it feeds the New York ISO.
When did Blanchard Road 1 Community Solar open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average New York home's 586 kWh a month in 2025. Methodology.