Wind power plant · Callahan, TX

BMP Wind (TX)

BMP Wind (TX) is a 340 MW wind power plant in Callahan County, Texas, operated by BMP Wind LLC. Its oldest generator still running came online in 2021. In 2025 it generated 870 GWh, about what 65,000 average Texas homes use in a year.

Capacity340 MWNameplate, September 2026
Generated870 GWhIn 2025
Capacity factor29%Share of the most it could make, 2025
Generators1Oldest from 2021

BMP Wind (TX) in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 15th largest, about 0.8% of the state's 45 GW of wind capacity.

Callahan County has 4 power plants of 1 MW or more with 676 MW in all; BMP Wind (TX) is 50% of that and the largest of 3 wind plants there.

Its capacity factor of 29% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Callahan County goes 19 hours a year without power, the 46th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020212022202320242025GWh 870
02004006008001,00020212022202320242025870

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

BMP Wind (TX) (outlined) and other plants in Callahan County, shaded. 32.289, -99.292.

Plant facts

Operator
BMP Wind LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Callahan County, TX
EIA plant ID
62809
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
BMP Onshore Wind Turbine 340 MW 2021 –

Questions

BMP Wind (TX), answered

How much power does BMP Wind (TX) produce?

BMP Wind (TX) has 340 MW of capacity from one generator. In 2025 it generated 870 GWh, 29% of the most it could have made running flat out all year (its capacity factor).

How many homes does BMP Wind (TX) power?

Its 2025 output of 870 GWh equals the yearly electricity use of about 65,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is BMP Wind (TX)?

BMP Wind (TX) is in Callahan County, Texas, at about 32.289°, -99.292°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Callahan County goes 19 hours a year without power, the 46th most of 240 counties in Texas. The county's page has the full outage record.

Who operates BMP Wind (TX)?

It is operated by BMP Wind LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did BMP Wind (TX) open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.