Natural gas power plant · Haywood, TN
Brownsville Peaking Power
Brownsville Peaking Power is a 460 MW natural gas power plant in Haywood County, Tennessee, operated by Tennessee Valley Authority. Its oldest generator still running came online in 1999. In 2025 it generated 119 GWh, about what 8,400 average Tennessee homes use in a year.
Brownsville Peaking Power in context
Among the 12 natural gas plants in Tennessee in the EIA's inventory, it is the 6th largest, about 6.8% of the state's 6.8 GW of natural gas capacity.
Haywood County has 5 power plants of 1 MW or more with 2.1 GW in all; Brownsville Peaking Power is 22% of that and the 2nd largest of 2 natural gas plants there.
Its capacity factor of 3% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Haywood County goes 3.2 hours a year without power, the 52nd most of 73 counties in Tennessee. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Brownsville Peaking Power (outlined) and other plants in Haywood County, shaded. 35.544, -89.198.
Plant facts
- Operator
- Tennessee Valley Authority
- Sector
- Electric Utility
- Grid operator
- TVA
- County
- Haywood County, TN
- EIA plant ID
- 55081
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 3 | Natural Gas Fired Combustion Turbine | 118 MW | 1999 | – |
| 4 | Natural Gas Fired Combustion Turbine | 118 MW | 1999 | – |
| 1 | Natural Gas Fired Combustion Turbine | 112 MW | 1999 | – |
| 2 | Natural Gas Fired Combustion Turbine | 112 MW | 1999 | – |
Nearby
Other plants in Haywood County
Questions
Brownsville Peaking Power, answered
How much power does Brownsville Peaking Power produce?
Brownsville Peaking Power has 460 MW of capacity from 4 generators. In 2025 it generated 119 GWh, 3% of the most it could have made running flat out all year (its capacity factor).
How many homes does Brownsville Peaking Power power?
Its 2025 output of 119 GWh equals the yearly electricity use of about 8,400 average Tennessee homes (1,180 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Brownsville Peaking Power?
Brownsville Peaking Power is in Haywood County, Tennessee, at about 35.544°, -89.198°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Haywood County goes 3.2 hours a year without power, the 52nd most of 73 counties in Tennessee. The county's page has the full outage record.
Who operates Brownsville Peaking Power?
It is operated by Tennessee Valley Authority (EIA sector: Electric Utility), and it feeds the Tennessee Valley Authority.
When did Brownsville Peaking Power open?
Its oldest generator still running came online in 1999.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Tennessee home's 1,180 kWh a month in 2025. Methodology.