Natural gas power plant · Haywood, TN
Lagoon Creek
Lagoon Creek is a 1.6 GW natural gas power plant in Haywood County, Tennessee, operated by Tennessee Valley Authority. Its oldest generator still running came online in 2001. In 2025 it generated 3.4 TWh, about what 244,000 average Tennessee homes use in a year.
Lagoon Creek in context
Among the 12 natural gas plants in Tennessee in the EIA's inventory, it is the 2nd largest, about 24% of the state's 6.8 GW of natural gas capacity.
Haywood County has 5 power plants of 1 MW or more with 2.1 GW in all; Lagoon Creek is 78% of that and the largest of 2 natural gas plants there.
Its capacity factor of 24% in 2025 is close to the 23% typical for natural gas plants across the US.
The average electricity customer in Haywood County goes 3.2 hours a year without power, the 52nd most of 73 counties in Tennessee. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Lagoon Creek (outlined) and other plants in Haywood County, shaded. 35.658, -89.396.
Plant facts
- Operator
- Tennessee Valley Authority
- Sector
- Electric Utility
- Grid operator
- TVA
- County
- Haywood County, TN
- EIA plant ID
- 7845
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| STG1 | Natural Gas Fired Combined Cycle | 258 MW | 2010 | – |
| CTG1 | Natural Gas Fired Combined Cycle | 173 MW | 2010 | – |
| CTG2 | Natural Gas Fired Combined Cycle | 173 MW | 2010 | – |
| GT10 | Natural Gas Fired Combustion Turbine | 86 MW | 2002 | – |
| GT11 | Natural Gas Fired Combustion Turbine | 86 MW | 2002 | – |
| GT12 | Natural Gas Fired Combustion Turbine | 86 MW | 2002 | – |
| GT9 | Natural Gas Fired Combustion Turbine | 86 MW | 2002 | – |
| GT1 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT2 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT3 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT4 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT5 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT6 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT7 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
| GT8 | Natural Gas Fired Combustion Turbine | 85 MW | 2001 | – |
Nearby
Other plants in Haywood County
Questions
Lagoon Creek, answered
How much power does Lagoon Creek produce?
Lagoon Creek has 1.6 GW of capacity from 15 generators. In 2025 it generated 3.4 TWh, 24% of the most it could have made running flat out all year (its capacity factor).
How many homes does Lagoon Creek power?
Its 2025 output of 3.4 TWh equals the yearly electricity use of about 244,000 average Tennessee homes (1,180 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Lagoon Creek?
Lagoon Creek is in Haywood County, Tennessee, at about 35.658°, -89.396°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Haywood County goes 3.2 hours a year without power, the 52nd most of 73 counties in Tennessee. The county's page has the full outage record.
Who operates Lagoon Creek?
It is operated by Tennessee Valley Authority (EIA sector: Electric Utility), and it feeds the Tennessee Valley Authority.
When did Lagoon Creek open?
Its oldest generator still running came online in 2001.