Natural gas power plant · Burlington, NJ
Burlington Generating Station
Burlington Generating Station is a 242 MW natural gas power plant in Burlington County, New Jersey, operated by Parkway Generation Operating, LLC. Its oldest generator still running came online in 2000. In 2025 it generated 53 GWh, about what 6,600 average New Jersey homes use in a year.
Burlington Generating Station in context
Among the 50 natural gas plants in New Jersey in the EIA's inventory, it is the 16th largest, about 2.0% of the state's 12 GW of natural gas capacity.
Burlington County has 40 power plants of 1 MW or more with 429 MW in all; Burlington Generating Station is 56% of that and the largest of 2 natural gas plants there.
Its capacity factor of 3% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Burlington County goes 6.7 hours a year without power, the 6th most of 21 counties in New Jersey. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Burlington Generating Station (outlined) and other plants in Burlington County, shaded. 40.077, -74.879.
Plant facts
- Operator
- Parkway Generation Operating, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Burlington County, NJ
- EIA plant ID
- 2399
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 121 | Natural Gas Fired Combustion Turbine | 61 MW | 2000 | – |
| 122 | Natural Gas Fired Combustion Turbine | 61 MW | 2000 | – |
| 123 | Natural Gas Fired Combustion Turbine | 61 MW | 2000 | – |
| 124 | Natural Gas Fired Combustion Turbine | 61 MW | 2000 | – |
Retired
| Generator | Technology | Capacity | Online | Retired |
|---|---|---|---|---|
| 101 | Natural Gas Fired Combined Cycle | 45 MW | 1993 | 2004 |
| 102 | Natural Gas Fired Combined Cycle | 45 MW | 1993 | 2004 |
| 103 | Natural Gas Fired Combined Cycle | 45 MW | 1993 | 2004 |
| 104 | Natural Gas Fired Combined Cycle | 45 MW | 1993 | 2004 |
| 105 | Natural Gas Fired Combined Cycle | 45 MW | 1972 | 2004 |
| 91 | Petroleum Liquids | 42 MW | 1972 | 2014 |
| 92 | Petroleum Liquids | 42 MW | 1972 | 2014 |
| 93 | Petroleum Liquids | 42 MW | 1972 | 2014 |
| 94 | Petroleum Liquids | 42 MW | 1972 | 2014 |
| 111 | Petroleum Liquids | 42 MW | 1972 | 2015 |
| 112 | Petroleum Liquids | 42 MW | 1972 | 2015 |
| 113 | Petroleum Liquids | 42 MW | 1972 | 2015 |
| 114 | Petroleum Liquids | 42 MW | 1972 | 2015 |
| 8 | Petroleum Liquids | 19 MW | 1967 | 2015 |
Nearby
Other plants in Burlington County
Questions
Burlington Generating Station, answered
How much power does Burlington Generating Station produce?
Burlington Generating Station has 242 MW of capacity from 4 generators. In 2025 it generated 53 GWh, 3% of the most it could have made running flat out all year (its capacity factor).
How many homes does Burlington Generating Station power?
Its 2025 output of 53 GWh equals the yearly electricity use of about 6,600 average New Jersey homes (670 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Burlington Generating Station?
Burlington Generating Station is in Burlington County, New Jersey, at about 40.077°, -74.879°. It is one of 40 power plants of 1 MW or more in the county. The average electricity customer in Burlington County goes 6.7 hours a year without power, the 6th most of 21 counties in New Jersey. The county's page has the full outage record.
Who operates Burlington Generating Station?
It is operated by Parkway Generation Operating, LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Burlington Generating Station open?
Its oldest generator still running came online in 2000.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average New Jersey home's 670 kWh a month in 2025. Methodology.