Wind power plant · Huerfano, CO
Busch Ranch II Wind Farm
Busch Ranch II Wind Farm is a 59 MW wind power plant in Huerfano County, Colorado, operated by Black Hills Electric Generation LLC. Its oldest generator still running came online in 2019. In 2025 it generated 139 GWh, about what 18,000 average Colorado homes use in a year.
Busch Ranch II Wind Farm in context
Among the 34 wind plants in Colorado in the EIA's inventory, it is the 28th largest, about 1.0% of the state's 5.9 GW of wind capacity.
Huerfano County has 4 power plants of 1 MW or more with 157 MW in all; Busch Ranch II Wind Farm is 38% of that and the 2nd largest of 4 wind plants there.
Its capacity factor of 27% in 2025 is lower than the 32% typical for wind plants across the US.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Busch Ranch II Wind Farm (outlined) and other plants in Huerfano County, shaded. 37.766, -104.430.
Plant facts
- Operator
- Black Hills Electric Generation LLC
- Sector
- IPP Non-CHP
- Grid operator
- PSCO
- County
- Huerfano County, CO
- EIA plant ID
- 62445
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| WT | Onshore Wind Turbine | 59 MW | 2019 | – |
Nearby
Other plants in Huerfano County
Questions
Busch Ranch II Wind Farm, answered
How much power does Busch Ranch II Wind Farm produce?
Busch Ranch II Wind Farm has 59 MW of capacity from one generator. In 2025 it generated 139 GWh, 27% of the most it could have made running flat out all year (its capacity factor).
How many homes does Busch Ranch II Wind Farm power?
Its 2025 output of 139 GWh equals the yearly electricity use of about 18,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Busch Ranch II Wind Farm?
Busch Ranch II Wind Farm is in Huerfano County, Colorado, at about 37.766°, -104.430°. It is one of 4 power plants of 1 MW or more in the county.
Who operates Busch Ranch II Wind Farm?
It is operated by Black Hills Electric Generation LLC (EIA sector: IPP Non-CHP), and it feeds Public Service Company of Colorado.
When did Busch Ranch II Wind Farm open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.