Natural gas power plant · Los Angeles, CA
Center Hybrid
Center Hybrid is a 60 MW natural gas power plant in Los Angeles County, California, operated by Southern California Edison Co. Its oldest generator still running came online in 2007. In 2025 it generated 2.0 GWh, about what 337 average California homes use in a year.
Center Hybrid in context
Among the 304 natural gas plants in California in the EIA's inventory, it is the 100th largest, about 0.1% of the state's 41 GW of natural gas capacity.
Los Angeles County has 254 power plants of 1 MW or more with 14 GW in all; Center Hybrid is 0% of that and the 20th largest of 52 natural gas plants there.
Its capacity factor of 0% in 2025 is lower than the 23% typical for natural gas plants across the US.
The average electricity customer in Los Angeles County goes 4.5 hours a year without power, the 41st most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Center Hybrid (outlined) and other plants in Los Angeles County, shaded. 33.930, -118.105.
Plant facts
- Operator
- Southern California Edison Co
- Sector
- Electric Utility
- Grid operator
- CISO
- County
- Los Angeles County, CA
- EIA plant ID
- 56475
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Natural Gas Fired Combustion Turbine | 50 MW | 2007 | – |
| BA1 | Batteries | 10 MW · 10 MWh | 2016 | – |
Questions
Center Hybrid, answered
How much power does Center Hybrid produce?
Center Hybrid has 60 MW of capacity from 2 generators. In 2025 it generated 2.0 GWh, 0% of the most it could have made running flat out all year (its capacity factor).
How many homes does Center Hybrid power?
Its 2025 output of 2.0 GWh equals the yearly electricity use of about 337 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Center Hybrid?
Center Hybrid is in Los Angeles County, California, at about 33.930°, -118.105°. It is one of 254 power plants of 1 MW or more in the county. The average electricity customer in Los Angeles County goes 4.5 hours a year without power, the 41st most of 56 counties in California. The county's page has the full outage record.
Who operates Center Hybrid?
It is operated by Southern California Edison Co (EIA sector: Electric Utility), and it feeds the California ISO.
When did Center Hybrid open?
Its oldest generator still running came online in 2007.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.