Storage power plant · Tarrant, TX
Century BESS
Century BESS is a 10 MW storage power plant in Tarrant County, Texas, operated by Prologis Logistics Services Incorporated BESS. Its oldest generator still running came online in 2024.
Century BESS in context
Among the 233 storage plants in Texas in the EIA's inventory, it is the 129th largest, about 0.1% of the state's 16 GW of storage capacity.
Tarrant County has 26 power plants of 1 MW or more with 1.5 GW in all; Century BESS is 1% of that and the 2nd largest of 4 storage plants there.
The average electricity customer in Tarrant County goes 5.4 hours a year without power, the 192nd most of 240 counties in Texas. The county's page has the full outage record.
Where it is
Century BESS (outlined) and other plants in Tarrant County, shaded. 32.687, -97.083.
Plant facts
- Operator
- Prologis Logistics Services Incorporated BESS
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Tarrant County, TX
- EIA plant ID
- 68684
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| DL805 | Batteries | 10 MW · 25 MWh | 2024 | – |
Nearby
Other plants in Tarrant County
Questions
Century BESS, answered
How much can Century BESS store and deliver?
Century BESS can deliver up to 10 MW and hold 25 MWh of energy, from one battery or storage system. Its net energy in 2025 was -0.9 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Century BESS?
Century BESS is in Tarrant County, Texas, at about 32.687°, -97.083°. It is one of 26 power plants of 1 MW or more in the county. The average electricity customer in Tarrant County goes 5.4 hours a year without power, the 192nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Century BESS?
It is operated by Prologis Logistics Services Incorporated BESS (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Century BESS open?
Its oldest generator still running came online in 2024.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.