Colgate is a 315 MW hydro power plant in Yuba County, California, operated by Yuba County Water Agency - (CA). Its oldest generator still running came online in 1969. In 2025 it generated 1.3 TWh, about what 212,000 average California homes use in a year.

Capacity315 MWNameplate, September 2026
Generated1.3 TWhIn 2025
Capacity factor46%Share of the most it could make, 2025
Generators2Oldest from 1969

Colgate in context

Among the 238 hydro plants in California in the EIA's inventory, it is the 3rd largest, about 3.1% of the state's 10 GW of hydro capacity.

Yuba County has 4 power plants of 1 MW or more with 367 MW in all; Colgate is 86% of that and the largest of 3 hydro plants there.

Its capacity factor of 46% in 2025 is higher than the 34% typical for hydro plants across the US.

The average electricity customer in Yuba County goes 16 hours a year without power, the 21st most of 56 counties in California. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,5002,00020182019202020212022202320242025GWh 1,259
05001,0001,5002,00020192021202320251,259

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Colgate (outlined) and other plants in Yuba County, shaded. 39.331, -121.192.

Plant facts

Operator
Yuba County Water Agency - (CA)
Sector
Electric Utility
Grid operator
CISO
County
Yuba County, CA
EIA plant ID
454
Where California's power comes from → California power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Conventional Hydroelectric 158 MW 1969 –
2 Conventional Hydroelectric 158 MW 1969 –

Nearby

Other plants in Yuba County

Narrows 2 · 47 MWG2 Energy Ostrom Road LLC · 3.5 MWDeadwood Creek · 2.0 MW

Questions

Colgate, answered

How much power does Colgate produce?

Colgate has 315 MW of capacity from 2 generators. In 2025 it generated 1.3 TWh, 46% of the most it could have made running flat out all year (its capacity factor).

How many homes does Colgate power?

Its 2025 output of 1.3 TWh equals the yearly electricity use of about 212,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Colgate?

Colgate is in Yuba County, California, at about 39.331°, -121.192°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Yuba County goes 16 hours a year without power, the 21st most of 56 counties in California. The county's page has the full outage record.

Who operates Colgate?

It is operated by Yuba County Water Agency - (CA) (EIA sector: Electric Utility), and it feeds the California ISO.

When did Colgate open?

Its oldest generator still running came online in 1969.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.