Solar power plant · Hertford, NC
Colice Hall Solar
Colice Hall Solar is a 17 MW solar power plant in Hertford County, North Carolina, operated by Colice Hall Solar LLC. Its oldest generator still running came online in 2023. In 2025 it generated 34 GWh, about what 2,700 average North Carolina homes use in a year.
Colice Hall Solar in context
Among the 756 solar plants in North Carolina in the EIA's inventory, it is the 80th largest, about 0.2% of the state's 7.1 GW of solar capacity.
Hertford County has 16 power plants of 1 MW or more with 223 MW in all; Colice Hall Solar is 8% of that and the 3rd largest of 16 solar plants there.
Its capacity factor of 23% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Hertford County goes 3.5 hours a year without power, the 92nd most of 100 counties in North Carolina. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Colice Hall Solar (outlined) and other plants in Hertford County, shaded. 36.323, -77.010.
Plant facts
- Operator
- Colice Hall Solar LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Hertford County, NC
- EIA plant ID
- 67172
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| COLIC | Solar Photovoltaic | 17 MW | 2023 | – |
Nearby
Other plants in Hertford County
Questions
Colice Hall Solar, answered
How much power does Colice Hall Solar produce?
Colice Hall Solar has 17 MW of capacity from one generator. In 2025 it generated 34 GWh, 23% of the most it could have made running flat out all year (its capacity factor).
How many homes does Colice Hall Solar power?
Its 2025 output of 34 GWh equals the yearly electricity use of about 2,700 average North Carolina homes (1,044 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Colice Hall Solar?
Colice Hall Solar is in Hertford County, North Carolina, at about 36.323°, -77.010°. It is one of 16 power plants of 1 MW or more in the county. The average electricity customer in Hertford County goes 3.5 hours a year without power, the 92nd most of 100 counties in North Carolina. The county's page has the full outage record.
Who operates Colice Hall Solar?
It is operated by Colice Hall Solar LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Colice Hall Solar open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average North Carolina home's 1,044 kWh a month in 2025. Methodology.