Solar power plant · Decatur, GA

Cool Springs Solar (Hybrid)

Cool Springs Solar (Hybrid) is a 253 MW solar power plant in Decatur County, Georgia, operated by Cool Springs Solar, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 514 GWh, about what 40,000 average Georgia homes use in a year.

Capacity253 MWNameplate, September 2026
Generated514 GWhIn 2025
Capacity factor23%Share of the most it could make, 2025
Generators2Oldest from 2021

Cool Springs Solar (Hybrid) in context

Among the 154 solar plants in Georgia in the EIA's inventory, it is the 3rd largest, about 4.4% of the state's 5.8 GW of solar capacity.

Decatur County has 7 power plants of 1 MW or more with 637 MW in all; Cool Springs Solar (Hybrid) is 40% of that and the largest of 6 solar plants there.

Its capacity factor of 23% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Decatur County goes 19 hours a year without power, the 34th most of 156 counties in Georgia. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

020040060020212022202320242025GWh 514
020040060020212022202320242025514

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Cool Springs Solar (Hybrid) (outlined) and other plants in Decatur County, shaded. 30.748, -84.680.

Plant facts

Operator
Cool Springs Solar, LLC
Sector
IPP Non-CHP
Grid operator
SOCO
County
Decatur County, GA
EIA plant ID
63721
  • Solar213 MW84%
  • Storage40 MW16%
Where Georgia's power comes from → Georgia power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
COOLS Solar Photovoltaic 213 MW 2021 –
CSBAT Batteries 40 MW · 80 MWh 2021 –

Questions

Cool Springs Solar (Hybrid), answered

How much power does Cool Springs Solar (Hybrid) produce?

Cool Springs Solar (Hybrid) has 253 MW of capacity from 2 generators. In 2025 it generated 514 GWh, 23% of the most it could have made running flat out all year (its capacity factor).

How many homes does Cool Springs Solar (Hybrid) power?

Its 2025 output of 514 GWh equals the yearly electricity use of about 40,000 average Georgia homes (1,077 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Cool Springs Solar (Hybrid)?

Cool Springs Solar (Hybrid) is in Decatur County, Georgia, at about 30.748°, -84.680°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Decatur County goes 19 hours a year without power, the 34th most of 156 counties in Georgia. The county's page has the full outage record.

Who operates Cool Springs Solar (Hybrid)?

It is operated by Cool Springs Solar, LLC (EIA sector: IPP Non-CHP), and it feeds Southern Company.

When did Cool Springs Solar (Hybrid) open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Georgia home's 1,077 kWh a month in 2025. Methodology.