Solar power plant · Salt Lake, UT

Copperton Solar Plant No. 1

Copperton Solar Plant No. 1 is a 30 MW solar power plant in Salt Lake County, Utah, operated by Kennecott Utah Copper. Its oldest generator still running came online in 2024. In 2025 it generated 7.3 GWh, about what 799 average Utah homes use in a year.

Capacity30 MWNameplate, September 2026
Generated7.3 GWhIn 2025
Capacity factor–Not a full year of data
Generators2Oldest from 2024

Copperton Solar Plant No. 1 in context

Among the 56 solar plants in Utah in the EIA's inventory, it is the 30th largest, about 1.0% of the state's 3.0 GW of solar capacity.

Salt Lake County has 16 power plants of 1 MW or more with 1.0 GW in all; Copperton Solar Plant No. 1 is 3% of that and the largest of 3 solar plants there.

The average electricity customer in Salt Lake County goes 3.6 hours a year without power, the 11th most of 23 counties in Utah. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

024681020242025GWh 7
0246810202420257

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Copperton Solar Plant No. 1 (outlined) and other plants in Salt Lake County, shaded. 40.577, -112.085.

Plant facts

Operator
Kennecott Utah Copper
Sector
Industrial Non-CHP
Grid operator
PACE
County
Salt Lake County, UT
EIA plant ID
64427
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CSP2 Solar Photovoltaic 25 MW 2025 –
CSP1 Solar Photovoltaic 5.0 MW 2024 –

Questions

Copperton Solar Plant No. 1, answered

How much power does Copperton Solar Plant No. 1 produce?

Copperton Solar Plant No. 1 has 30 MW of capacity from 2 generators. In 2025 it generated 7.3 GWh.

How many homes does Copperton Solar Plant No. 1 power?

Its 2025 output of 7.3 GWh equals the yearly electricity use of about 799 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Copperton Solar Plant No. 1?

Copperton Solar Plant No. 1 is in Salt Lake County, Utah, at about 40.577°, -112.085°. It is one of 16 power plants of 1 MW or more in the county. The average electricity customer in Salt Lake County goes 3.6 hours a year without power, the 11th most of 23 counties in Utah. The county's page has the full outage record.

Who operates Copperton Solar Plant No. 1?

It is operated by Kennecott Utah Copper (EIA sector: Industrial Non-CHP), and it feeds PacifiCorp East.

When did Copperton Solar Plant No. 1 open?

Its oldest generator still running came online in 2024.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.