Storage power plant · Maricopa, AZ
Cotton Center Solar Hybrid
Cotton Center Solar Hybrid is a 34 MW storage power plant in Maricopa County, Arizona, operated by Arizona Public Service Co. Its oldest generator still running came online in 2011. In 2025 it generated 29 GWh, about what 2,400 average Arizona homes use in a year.
Cotton Center Solar Hybrid in context
Among the 41 storage plants in Arizona in the EIA's inventory, it is the 34th largest, about 0.5% of the state's 6.3 GW of storage capacity.
Maricopa County has 82 power plants of 1 MW or more with 24 GW in all; Cotton Center Solar Hybrid is 0% of that and the 18th largest of 21 storage plants there.
The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Cotton Center Solar Hybrid (outlined) and other plants in Maricopa County, shaded. 33.035, -112.662.
Plant facts
- Operator
- Arizona Public Service Co
- Sector
- Electric Utility
- Grid operator
- AZPS
- County
- Maricopa County, AZ
- EIA plant ID
- 57561
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| PV1 | Solar Photovoltaic | 17 MW | 2011 | – |
| CC17M | Batteries | 17 MW · 51 MWh | 2023 | – |
Questions
Cotton Center Solar Hybrid, answered
How much can Cotton Center Solar Hybrid store and deliver?
Cotton Center Solar Hybrid can deliver up to 34 MW and hold 51 MWh of energy, from 2 storage units. Its net energy in 2025 was 29 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Cotton Center Solar Hybrid?
Cotton Center Solar Hybrid is in Maricopa County, Arizona, at about 33.035°, -112.662°. It is one of 82 power plants of 1 MW or more in the county. The average electricity customer in Maricopa County goes 1.5 hours a year without power, the 7th most of 11 counties in Arizona. The county's page has the full outage record.
Who operates Cotton Center Solar Hybrid?
It is operated by Arizona Public Service Co (EIA sector: Electric Utility), and it feeds Arizona Public Service.
When did Cotton Center Solar Hybrid open?
Its oldest generator still running came online in 2011.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Arizona home's 1,030 kWh a month in 2025. Methodology.