Wind power plant · Kit Carson, CO

Crossing Trails Wind Power Project LLC.

Crossing Trails Wind Power Project LLC. is a 104 MW wind power plant in Kit Carson County, Colorado, operated by EDP Renewables North America LLC. Its oldest generator still running came online in 2021. In 2025 it generated 394 GWh, about what 50,000 average Colorado homes use in a year.

Capacity104 MWNameplate, September 2026
Generated394 GWhIn 2025
Capacity factor43%Share of the most it could make, 2025
Generators1Oldest from 2021

Crossing Trails Wind Power Project LLC. in context

Among the 34 wind plants in Colorado in the EIA's inventory, it is the 21st largest, about 1.8% of the state's 5.9 GW of wind capacity.

Kit Carson County has 7 power plants of 1 MW or more with 1.4 GW in all; Crossing Trails Wind Power Project LLC. is 7% of that and the 5th largest of 6 wind plants there.

Its capacity factor of 43% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Kit Carson County goes 12 hours a year without power, the 5th most of 39 counties in Colorado. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030040050020212022202320242025GWh 394
010020030040050020212022202320242025394

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Crossing Trails Wind Power Project LLC. (outlined) and other plants in Kit Carson County, shaded. 39.047, -102.822.

Plant facts

Operator
EDP Renewables North America LLC
Sector
IPP Non-CHP
Grid operator
WACM
County
Kit Carson County, CO
EIA plant ID
62489
Where Colorado's power comes from → Colorado power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GEN1 Onshore Wind Turbine 104 MW 2021 –

Questions

Crossing Trails Wind Power Project LLC., answered

How much power does Crossing Trails Wind Power Project LLC. produce?

Crossing Trails Wind Power Project LLC. has 104 MW of capacity from one generator. In 2025 it generated 394 GWh, 43% of the most it could have made running flat out all year (its capacity factor).

How many homes does Crossing Trails Wind Power Project LLC. power?

Its 2025 output of 394 GWh equals the yearly electricity use of about 50,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Crossing Trails Wind Power Project LLC.?

Crossing Trails Wind Power Project LLC. is in Kit Carson County, Colorado, at about 39.047°, -102.822°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Kit Carson County goes 12 hours a year without power, the 5th most of 39 counties in Colorado. The county's page has the full outage record.

Who operates Crossing Trails Wind Power Project LLC.?

It is operated by EDP Renewables North America LLC (EIA sector: IPP Non-CHP), and it feeds WAPA Rocky Mountain.

When did Crossing Trails Wind Power Project LLC. open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.