Wind power plant · Roger Mills, OK
Dempsey Ridge Wind Farm
Dempsey Ridge Wind Farm is a 132 MW wind power plant in Roger Mills County, Oklahoma, operated by Acciona Wind Energy USA LLC. Its oldest generator still running came online in 2012. In 2025 it generated 118 GWh, about what 9,300 average Oklahoma homes use in a year.
Dempsey Ridge Wind Farm in context
Among the 70 wind plants in Oklahoma in the EIA's inventory, it is the 45th largest, about 1.0% of the state's 13 GW of wind capacity.
Roger Mills County has 3 power plants of 1 MW or more with 453 MW in all; Dempsey Ridge Wind Farm is 29% of that and the 2nd largest of 3 wind plants there.
Its capacity factor of 10% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Roger Mills County goes 16 hours a year without power, the 5th most of 75 counties in Oklahoma. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Dempsey Ridge Wind Farm (outlined) and other plants in Roger Mills County, shaded. 35.530, -99.814.
Plant facts
- Operator
- Acciona Wind Energy USA LLC
- Sector
- IPP Non-CHP
- Grid operator
- SWPP
- County
- Roger Mills County, OK
- EIA plant ID
- 56665
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| DR | Onshore Wind Turbine | 132 MW | 2012 | – |
Nearby
Other plants in Roger Mills County
Questions
Dempsey Ridge Wind Farm, answered
How much power does Dempsey Ridge Wind Farm produce?
Dempsey Ridge Wind Farm has 132 MW of capacity from one generator. In 2025 it generated 118 GWh, 10% of the most it could have made running flat out all year (its capacity factor).
How many homes does Dempsey Ridge Wind Farm power?
Its 2025 output of 118 GWh equals the yearly electricity use of about 9,300 average Oklahoma homes (1,064 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Dempsey Ridge Wind Farm?
Dempsey Ridge Wind Farm is in Roger Mills County, Oklahoma, at about 35.530°, -99.814°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Roger Mills County goes 16 hours a year without power, the 5th most of 75 counties in Oklahoma. The county's page has the full outage record.
Who operates Dempsey Ridge Wind Farm?
It is operated by Acciona Wind Energy USA LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.
When did Dempsey Ridge Wind Farm open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Oklahoma home's 1,064 kWh a month in 2025. Methodology.