Wind power plant · Knox, TX

El Campo Wind

El Campo Wind is a 243 MW wind power plant in Knox County, Texas, operated by El Campo Wind, LLC (Longroad). Its oldest generator still running came online in 2020. In 2025 it generated 840 GWh, about what 63,000 average Texas homes use in a year.

Capacity243 MWNameplate, September 2026
Generated840 GWhIn 2025
Capacity factor40%Share of the most it could make, 2025
Generators1Oldest from 2020

El Campo Wind in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 55th largest, about 0.5% of the state's 45 GW of wind capacity.

Knox County has 4 power plants of 1 MW or more with 954 MW in all; El Campo Wind is 25% of that and the 2nd largest of 4 wind plants there.

Its capacity factor of 40% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Knox County goes 12 hours a year without power, the 102nd most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,000202020212022202320242025GWh 840
02004006008001,000202020212022202320242025840

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

El Campo Wind (outlined) and other plants in Knox County, shaded. 33.732, -99.726.

Plant facts

Operator
El Campo Wind, LLC (Longroad)
Sector
IPP Non-CHP
Grid operator
ERCO
County
Knox County, TX
EIA plant ID
62765
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CAMPO Onshore Wind Turbine 243 MW 2020 –

Questions

El Campo Wind, answered

How much power does El Campo Wind produce?

El Campo Wind has 243 MW of capacity from one generator. In 2025 it generated 840 GWh, 40% of the most it could have made running flat out all year (its capacity factor).

How many homes does El Campo Wind power?

Its 2025 output of 840 GWh equals the yearly electricity use of about 63,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is El Campo Wind?

El Campo Wind is in Knox County, Texas, at about 33.732°, -99.726°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Knox County goes 12 hours a year without power, the 102nd most of 240 counties in Texas. The county's page has the full outage record.

Who operates El Campo Wind?

It is operated by El Campo Wind, LLC (Longroad) (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did El Campo Wind open?

Its oldest generator still running came online in 2020.