Solar power plant · Freestone, TX
Fairfield Solar Project
Fairfield Solar Project is a 10 MW solar power plant in Freestone County, Texas, operated by Ellomay USA Inc. Its oldest generator still running came online in 2025. In 2025 it generated 14 GWh, about what 1,100 average Texas homes use in a year.
Fairfield Solar Project in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 200th largest, about 0.0% of the state's 37 GW of solar capacity.
Freestone County has 3 power plants of 1 MW or more with 1.5 GW in all; Fairfield Solar Project is 1% of that.
The average electricity customer in Freestone County goes 23 hours a year without power, the 32nd most of 240 counties in Texas. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Fairfield Solar Project (outlined) and other plants in Freestone County, shaded. 31.714, -96.187.
Plant facts
- Operator
- Ellomay USA Inc
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Freestone County, TX
- EIA plant ID
- 69263
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| FRFWS | Solar Photovoltaic | 10 MW | 2025 | – |
Nearby
Other plants in Freestone County
Questions
Fairfield Solar Project, answered
How much power does Fairfield Solar Project produce?
Fairfield Solar Project has 10 MW of capacity from one generator. In 2025 it generated 14 GWh.
How many homes does Fairfield Solar Project power?
Its 2025 output of 14 GWh equals the yearly electricity use of about 1,100 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Fairfield Solar Project?
Fairfield Solar Project is in Freestone County, Texas, at about 31.714°, -96.187°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Freestone County goes 23 hours a year without power, the 32nd most of 240 counties in Texas. The county's page has the full outage record.
Who operates Fairfield Solar Project?
It is operated by Ellomay USA Inc (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Fairfield Solar Project open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.