Solar power plant · Beaver, PA
Gaucho Solar
Gaucho Solar is a 20 MW solar power plant in Beaver County, Pennsylvania, operated by Gaucho Solar. Its oldest generator still running came online in 2023. In 2025 it generated 32 GWh, about what 3,200 average Pennsylvania homes use in a year.
Gaucho Solar in context
Among the 82 solar plants in Pennsylvania in the EIA's inventory, it is the 19th largest, about 1.6% of the state's 1.2 GW of solar capacity.
Beaver County has 8 power plants of 1 MW or more with 2.2 GW in all; Gaucho Solar is 1% of that and the largest of 4 solar plants there.
Its capacity factor of 18% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Beaver County goes 6.5 hours a year without power, the 34th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Gaucho Solar (outlined) and other plants in Beaver County, shaded. 40.512, -80.313.
Plant facts
- Operator
- Gaucho Solar
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Beaver County, PA
- EIA plant ID
- 65214
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GCHOS | Solar Photovoltaic | 20 MW | 2023 | – |
Nearby
Other plants in Beaver County
Questions
Gaucho Solar, answered
How much power does Gaucho Solar produce?
Gaucho Solar has 20 MW of capacity from one generator. In 2025 it generated 32 GWh, 18% of the most it could have made running flat out all year (its capacity factor).
How many homes does Gaucho Solar power?
Its 2025 output of 32 GWh equals the yearly electricity use of about 3,200 average Pennsylvania homes (839 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Gaucho Solar?
Gaucho Solar is in Beaver County, Pennsylvania, at about 40.512°, -80.313°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Beaver County goes 6.5 hours a year without power, the 34th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Who operates Gaucho Solar?
It is operated by Gaucho Solar (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Gaucho Solar open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Pennsylvania home's 839 kWh a month in 2025. Methodology.