Solar power plant · Beaver, PA
Pine 2 Solar
Pine 2 Solar is a 17 MW solar power plant in Beaver County, Pennsylvania, operated by BE-Pine2 LLC. Its oldest generator still running came online in 2023. In 2025 it generated 29 GWh, about what 2,800 average Pennsylvania homes use in a year.
Pine 2 Solar in context
Among the 82 solar plants in Pennsylvania in the EIA's inventory, it is the 28th largest, about 1.4% of the state's 1.2 GW of solar capacity.
Beaver County has 8 power plants of 1 MW or more with 2.2 GW in all; Pine 2 Solar is 1% of that and the 3rd largest of 4 solar plants there.
Its capacity factor of 19% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Beaver County goes 6.5 hours a year without power, the 34th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Pine 2 Solar (outlined) and other plants in Beaver County, shaded. 40.616, -80.471.
Plant facts
- Operator
- BE-Pine2 LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Beaver County, PA
- EIA plant ID
- 66944
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2-115 | Solar Photovoltaic | 17 MW | 2023 | – |
Nearby
Other plants in Beaver County
Questions
Pine 2 Solar, answered
How much power does Pine 2 Solar produce?
Pine 2 Solar has 17 MW of capacity from one generator. In 2025 it generated 29 GWh, 19% of the most it could have made running flat out all year (its capacity factor).
How many homes does Pine 2 Solar power?
Its 2025 output of 29 GWh equals the yearly electricity use of about 2,800 average Pennsylvania homes (839 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Pine 2 Solar?
Pine 2 Solar is in Beaver County, Pennsylvania, at about 40.616°, -80.471°. It is one of 8 power plants of 1 MW or more in the county. The average electricity customer in Beaver County goes 6.5 hours a year without power, the 34th most of 67 counties in Pennsylvania. The county's page has the full outage record.
Who operates Pine 2 Solar?
It is operated by BE-Pine2 LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Pine 2 Solar open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Pennsylvania home's 839 kWh a month in 2025. Methodology.