Wind power plant · Laramie, WY
Happy Jack Windpower Project
Happy Jack Windpower Project is a 29 MW wind power plant in Laramie County, Wyoming, operated by Deriva Energy. Its oldest generator still running came online in 2008. In 2025 it generated 59 GWh, about what 5,900 average Wyoming homes use in a year.
Happy Jack Windpower Project in context
Among the 28 wind plants in Wyoming in the EIA's inventory, it is the 27th largest, about 0.6% of the state's 4.7 GW of wind capacity.
Laramie County has 7 power plants of 1 MW or more with 746 MW in all; Happy Jack Windpower Project is 4% of that and the 5th largest of 5 wind plants there.
Its capacity factor of 23% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Laramie County goes 1.0 hours a year without power, the 17th most of 20 counties in Wyoming. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Happy Jack Windpower Project (outlined) and other plants in Laramie County, shaded. 41.140, -104.998.
Plant facts
- Operator
- Deriva Energy
- Sector
- IPP Non-CHP
- Grid operator
- WAUW
- County
- Laramie County, WY
- EIA plant ID
- 56960
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| HJW01 | Onshore Wind Turbine | 29 MW | 2008 | – |
Questions
Happy Jack Windpower Project, answered
How much power does Happy Jack Windpower Project produce?
Happy Jack Windpower Project has 29 MW of capacity from one generator. In 2025 it generated 59 GWh, 23% of the most it could have made running flat out all year (its capacity factor).
How many homes does Happy Jack Windpower Project power?
Its 2025 output of 59 GWh equals the yearly electricity use of about 5,900 average Wyoming homes (835 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Happy Jack Windpower Project?
Happy Jack Windpower Project is in Laramie County, Wyoming, at about 41.140°, -104.998°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Laramie County goes 1.0 hours a year without power, the 17th most of 20 counties in Wyoming. The county's page has the full outage record.
Who operates Happy Jack Windpower Project?
It is operated by Deriva Energy (EIA sector: IPP Non-CHP), and it feeds balancing authority WAUW.
When did Happy Jack Windpower Project open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Wyoming home's 835 kWh a month in 2025. Methodology.