Hydro power plant · Wasatch, UT
Jordanelle Dam Hydroelectric Project
Jordanelle Dam Hydroelectric Project is a 13 MW hydro power plant in Wasatch County, Utah, operated by Central Utah Water Conservancy District. Its oldest generator still running came online in 2008. In 2025 it generated 49 GWh, about what 5,400 average Utah homes use in a year.
Jordanelle Dam Hydroelectric Project in context
Among the 29 hydro plants in Utah in the EIA's inventory, it is the 3rd largest, about 4.9% of the state's 264 MW of hydro capacity.
Wasatch County has 5 power plants of 1 MW or more with 38 MW in all; Jordanelle Dam Hydroelectric Project is 34% of that and the largest of 4 hydro plants there.
Its capacity factor of 43% in 2025 is higher than the 34% typical for hydro plants across the US.
The average electricity customer in Wasatch County goes 1.6 hours a year without power, the 21st most of 23 counties in Utah. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Jordanelle Dam Hydroelectric Project (outlined) and other plants in Wasatch County, shaded. 40.597, -111.424.
Plant facts
- Operator
- Central Utah Water Conservancy District
- Sector
- Commercial Non-CHP
- Grid operator
- PACE
- County
- Wasatch County, UT
- EIA plant ID
- 61853
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN 1 | Conventional Hydroelectric | 6.5 MW | 2008 | – |
| GEN 2 | Conventional Hydroelectric | 6.5 MW | 2008 | – |
Nearby
Other plants in Wasatch County
Questions
Jordanelle Dam Hydroelectric Project, answered
How much power does Jordanelle Dam Hydroelectric Project produce?
Jordanelle Dam Hydroelectric Project has 13 MW of capacity from 2 generators. In 2025 it generated 49 GWh, 43% of the most it could have made running flat out all year (its capacity factor).
How many homes does Jordanelle Dam Hydroelectric Project power?
Its 2025 output of 49 GWh equals the yearly electricity use of about 5,400 average Utah homes (761 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Jordanelle Dam Hydroelectric Project?
Jordanelle Dam Hydroelectric Project is in Wasatch County, Utah, at about 40.597°, -111.424°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Wasatch County goes 1.6 hours a year without power, the 21st most of 23 counties in Utah. The county's page has the full outage record.
Who operates Jordanelle Dam Hydroelectric Project?
It is operated by Central Utah Water Conservancy District (EIA sector: Commercial Non-CHP), and it feeds PacifiCorp East.
When did Jordanelle Dam Hydroelectric Project open?
Its oldest generator still running came online in 2008.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Utah home's 761 kWh a month in 2025. Methodology.