Hydro power plant · Shasta, CA
Keswick
Keswick is a 117 MW hydro power plant in Shasta County, California, operated by U S Bureau of Reclamation. Its oldest generator still running came online in 1949. In 2025 it generated 407 GWh, about what 69,000 average California homes use in a year.
Keswick in context
Among the 238 hydro plants in California in the EIA's inventory, it is the 30th largest, about 1.1% of the state's 10 GW of hydro capacity.
Shasta County has 37 power plants of 1 MW or more with 2.4 GW in all; Keswick is 5% of that and the 6th largest of 28 hydro plants there.
Its capacity factor of 40% in 2025 is higher than the 34% typical for hydro plants across the US.
The average electricity customer in Shasta County goes 21 hours a year without power, the 18th most of 56 counties in California. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Keswick (outlined) and other plants in Shasta County, shaded. 40.612, -122.446.
Plant facts
- Operator
- U S Bureau of Reclamation
- Sector
- Electric Utility
- Grid operator
- BANC
- County
- Shasta County, CA
- EIA plant ID
- 443
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 2 | Conventional Hydroelectric | 39 MW | 1949 | – |
| 3 | Conventional Hydroelectric | 39 MW | 1949 | – |
| 1 | Conventional Hydroelectric | 39 MW | 1950 | – |
Nearby
Other plants in Shasta County
Questions
Keswick, answered
How much power does Keswick produce?
Keswick has 117 MW of capacity from 3 generators. In 2025 it generated 407 GWh, 40% of the most it could have made running flat out all year (its capacity factor).
How many homes does Keswick power?
Its 2025 output of 407 GWh equals the yearly electricity use of about 69,000 average California homes (494 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Keswick?
Keswick is in Shasta County, California, at about 40.612°, -122.446°. It is one of 37 power plants of 1 MW or more in the county. The average electricity customer in Shasta County goes 21 hours a year without power, the 18th most of 56 counties in California. The county's page has the full outage record.
Who operates Keswick?
It is operated by U S Bureau of Reclamation (EIA sector: Electric Utility), and it feeds balancing authority BANC.
When did Keswick open?
Its oldest generator still running came online in 1949.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average California home's 494 kWh a month in 2025. Methodology.