Natural gas power plant · Middlesex, CT

Kleen Energy Systems

Kleen Energy Systems is a 693 MW natural gas power plant in Middlesex County, Connecticut, operated by Kleen Energy Systems, LLC. Its oldest generator still running came online in 2011. In 2025 it generated 3.2 TWh, about what 381,000 average Connecticut homes use in a year.

Capacity693 MWNameplate, September 2026
Generated3.2 TWhIn 2025
Capacity factor53%Share of the most it could make, 2025
Generators3Oldest from 2011

Kleen Energy Systems in context

Among the 48 natural gas plants in Connecticut in the EIA's inventory, it is the 3rd largest, about 14% of the state's 5.0 GW of natural gas capacity.

Middlesex County has 9 power plants of 1 MW or more with 1.7 GW in all; Kleen Energy Systems is 40% of that and the largest of 3 natural gas plants there.

Its capacity factor of 53% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Middlesex County goes 9.5 hours a year without power, the 4th most of 8 counties in Connecticut. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

01,0002,0003,0004,00020182019202020212022202320242025GWh 3,216
01,0002,0003,0004,00020192021202320253,216

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Kleen Energy Systems (outlined) and other plants in Middlesex County, shaded. 41.553, -72.597.

Plant facts

Operator
Kleen Energy Systems, LLC
Sector
IPP Non-CHP
Grid operator
ISNE
County
Middlesex County, CT
EIA plant ID
56798
Where Connecticut's power comes from → Connecticut power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
ST Natural Gas Fired Combined Cycle 295 MW 2011 –
U1 Natural Gas Fired Combined Cycle 199 MW 2011 –
U2 Natural Gas Fired Combined Cycle 199 MW 2011 –

Nearby

Other plants in Middlesex County

Middletown · 786 MWGenConn Middletown LLC · 242 MWWesleyan University Cogen 1 · 2.4 MWCP East Hampton I & II Solar · 2.0 MWFedEx Middletown · 1.5 MWCP Middletown Solar I LLC · 1.0 MWCP Middletown Solar II LLC · 1.0 MWFDX010.0 FedEx Fuel Cell · 1.0 MW

Questions

Kleen Energy Systems, answered

How much power does Kleen Energy Systems produce?

Kleen Energy Systems has 693 MW of capacity from 3 generators. In 2025 it generated 3.2 TWh, 53% of the most it could have made running flat out all year (its capacity factor).

How many homes does Kleen Energy Systems power?

Its 2025 output of 3.2 TWh equals the yearly electricity use of about 381,000 average Connecticut homes (704 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Kleen Energy Systems?

Kleen Energy Systems is in Middlesex County, Connecticut, at about 41.553°, -72.597°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Middlesex County goes 9.5 hours a year without power, the 4th most of 8 counties in Connecticut. The county's page has the full outage record.

Who operates Kleen Energy Systems?

It is operated by Kleen Energy Systems, LLC (EIA sector: IPP Non-CHP), and it feeds ISO New England.

When did Kleen Energy Systems open?

Its oldest generator still running came online in 2011.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Connecticut home's 704 kWh a month in 2025. Methodology.